Maico Centro-E Installation And Operating Instructions Manual Download Page 7

9 Commissioning

7

11.Ensure that the spiral housing is correctly en-

gaged. To do this, gently pull and press
against the spiral housing. The spiral housing
must not move in the process. Alternatively,
screw the spiral housing tightly into the hous-
ing → previous figure.

8.4 Installing the cover

15

Cover with central screw [15.1]

16

Regulating plate for second room connec-
tion

17

Filter mat, filter class G2

Installation information

• Cover can be turned up to ± 5° (to provide com-

pensation if housing is inserted at too much of
an angle). If installing on a wall, ensure that the
Maico name is in the bottom right.

• If the housing edge is flush with the plaster, use

central screw, M6 x 16 mm, to secure the
cover.

• With a plaster overshoot of up to 20 mm to the

housing edge, use spacing frame DR 60/100
between the wall and cover. The customer
should provide a longer screw (M6 fillister head)
to secure the cover.

• If the housing is plastered in too deep, com-

pensate for this with a two-part wall frame ER-
MR (can be adjusted between 50...100 mm).
This prevents air from being drawn in from the
shaft. Use the supplied screw to fix the cover.

1. Fold up cover at the recessed grip, place on

the housing and secure with the central screw.

2. If necessary, first fit a spacing or wall frame.

3. With second room extraction, insert regulating

plate below locking tabs at the side on the in-
take grille of the cover, insert filter mat.

4. Lock cover. The lock must engage audibly.

5. Switch on mains fuse, remove warning sign.

6. Undertake initial commissioning and function

test.

7. Affix time strip (supplied with the cover) and

push the activation button [A] all the way. In-
stallation location of time strip, e.g. near the
cover.

The red dye in the interior of the 
bar [B] is released. The 
bar indicator first fills 
slightly. Within the 
next 6 months, the bar 
indicator [B] will rise to the 
upper edge (indicator value 6).

9 Commissioning

1. Switch on mains fuse and remove warning

sign.

2. Run function test. To do this, switch unit on

and off, observe delay times (for control mod-
els Controls (circuit board types)).

3. Check that the unit is running smoothly. It is

also important that the air can flow un-
hindered.

4. Switch off unit.

10 Operating the unit

Centro-M

No operation of the standalone unit is possible. It
is used in systems with a jointly variable volumet-
ric flow. In combination with a timer and a step
transformer, the volumetric air flow of the entire
air extraction system can be controlled centrally.

Centro-E

Exhaust air element with servomotor. For use in
systems with variable volumetric flows for indi-
vidual apartments. Basic and demand-based
ventilation can be switched on and off via a light

Summary of Contents for Centro-E

Page 1: ...Installation and operating instructions Flush mounted exhaust air elements for Centro centralised ventilation system according to DIN 18017 3 Centro M Centro E Centro H www maico ventilatoren com...

Page 2: ...s 4 6 Technical data 4 6 1 Environmental conditions and oper ating limits 4 6 2 Regulations for operation with fire places 4 6 3 Technical data table 5 6 4 Storage 5 7 Mounting preparations 5 8 Instal...

Page 3: ...ate in terior bathrooms toilet rooms and open plan kit chens with exterior windows storage rooms etc After completion of the interior building work the exhaust air elements are inserted into the flush...

Page 4: ...d housing Shaft level difference according to DIN 4109 tested by IAB Oberursel The Institute for Acoustics and Building Physics in Germany Cover with exhaust air filter and time strip Air filters are...

Page 5: ...table dry room Ambient temperature 10 C to 60 C Maico accepts no liability for corrosion damage caused by improper storage e g storage in a damp environment 7 Mounting preparations Suitable mounting m...

Page 6: ...sk of damage if ESD sensitive com ponents on the board are touched Avoid direct touching of the components or con tact surfaces NOTICE The noise level will increase if the housing floor seal is fitted...

Page 7: ...y first fit a spacing or wall frame 3 With second room extraction insert regulating plate below locking tabs at the side on the in take grille of the cover insert filter mat 4 Lock cover The lock must...

Page 8: ...reference value during opera tion the newly established reference value is saved The exhaust air element then automatic ally switches back to base load operation or to Off Demand based ventilation aut...

Page 9: ...15 minutes and resets the refer ence value Additional consumers connected to terminal 4 Damage to the unit if connected incorrectly Do not connect addi tional consumers to ter minal 4 The unit may onl...

Page 10: ...rior to accessing the connection terminals switch off all supply circuits Switch off mains fuse secure against being accidentally switched back on and position a visible warning sign 1 Remove spiral h...

Page 11: ...Notes...

Page 12: ...Maico Elektroapparate Fabrik GmbH Steinbeisstr 20 78056 Villingen Schwenningen Deutschland Service 49 7720 6940 info maico de D07 21_EN_DSW AV...

Reviews: