4 - Installation
DynaWave| OEM Contactless NFC Module | Installation and Operation Manual
Page 31 of 39 (
D998200265-10
)
4
Installation
This section provides an example of possible instructions to install DynaWave in a specific solution.
They are not designed to be distributed as-is to installing technicians. The solution design team must
develop solution-specific installation instructions, and may use these steps as a starting point.
FIRE RISK: If the device is being installed in a location near combustible materials, it is
critical to power down the whole system where it is being installed before installation to
avoid risk of fire or explosion. In these cases, follow the installation site’s standard Lock-
Out/Tag-Out procedures to prevent accidental power-on before installation is complete.
IF YOU CAN NOT GUARANTEE POWER WILL REMAIN OFF DURING
INSTALLATION, DO NOT PROCEED.
1)
See section
for important information about handling the device before installation.
2)
Make sure the power supply to the whole system is turned off and locked off.
3)
Route all cables, then connect the ground cable first, then connect all other cables.
4)
Tie cables down as specified by the solution design.
5)
Line up the four holes on the mounting face of the device with the mounting hardware (usually studs
or screws) on the enclosure’s mounting panel. If the solution design includes an enclosure, make sure
the gasket is installed, then insert the device into the mounting hole cutout.
6)
Inspect the device and enclosure from the front to make sure the device is pushed all the way into the
cutout. The device should be square, even, and flush with all four sides of the cutout. Some
enclosures with tighter tolerances may require additional force to push the device into place.
7)
Tighten the mounting hardware to half of the final torque using a diagonal pattern (e.g., upper right,
lower left, upper left, lower right). This is important to create even pressure around the whole gasket.
8)
Re-inspect to make sure the device is still positioned properly in the cutout.
9)
Tighten the mounting hardware, again in a diagonal pattern, to the full torque.
10)
Finish up any additional installation steps specified by the solution design, such as re-securing the
enclosure, cleaning the device, and installing any trade dress.
11)
Restore power to the system.
12)
Test the connection between the host and the device.