background image

 

Installation instructions 
Ultrasonic water meter 
ElecTo Bulk   

Important  

Before installing the meter, please read this manual carefully.  

This instruction sheet is for qualified technicians and does not contain the basic installation instructions.  

The design and specifications of the meter may change and may not correspond to the description contained in these 
instructions. In this event refer to the meter. These changes do not affect meter operation. For information contact the 
manufacturer. 

ElecTo Bulk  is a precision instrument. Before leaving the factory it undergoes strict tests and is intended to be used by 
qualified personnel. 

If the meter fails to operate properly or requires repair, contact the manufacturer or an authorised dealer. 

Do not shorten or lengthen the cable. This might affect meter performance. 

The  meters  undergo  strict  tests  before  leaving  the  factory.  Maintenance,  replacement  of  components  and  calibration 
must be carried out only by qualified personnel.  

Contact the manufacturer for technical support.  

In  the  event  of  loss  of  measuring  data  due  to  malfunction  or  other  causes,  the  manufacturer  commits  to  recover  the 
data. The manufacturer undertakes no responsibility if the loss of measuring data is caused by the user or by failure to 
back up data. 

The meter may be provided with a built-in pressure sensor for pipe pressure monitoring (optional). 

Choice of the water meter 

Before installing the meter ensure that the nominal diameter, nominal flow rate, working temperature and pressure are 
compatible with the operating conditions. 

Transport and storage 

Water meters are precision instruments: handle with care and protect from shocks and vibration. 

Store the meters in a frost-free place. Defrosting of the meter is a delicate operation. 

Store the meters in a dry place, at a temperature between 0 °C and +50 °C. Do not expose to direct sunlight. 

Recommendations for the installation 

Before installing the meter check that the two pipe sections are  aligned in order to avoid mechanical stress. Clean the 
two pipe sections carefully (especially if the system is empty) and allow water to flow in the pipe for some time using a 
pipe section instead of the meter. 

If  there  is  no  water  in  the  system,  open  the  upstream  valve  before  installing  the  meter.  This  is  necessary  to  avoid 
negative  pressure  from  building  when  opening  the  valve  at  the  end  of  the  installation  procedure  because  it  might 
damage the meter. 

If the meter is installed in vertical or inclined position, the pipe must always be full of water. 

Install the meter where it will be safe from frost (if necessary protect the meter with insulating material) and possibly in 
the lowest part of the system to prevent air from building up. 

Install the meter in a place where it will be protected from tampering and impact, and where it can be read easily. 

Install the meter ensuring that the flow direction arrow on the body points in the same direction as the flow. 

It is advisable to install a valve upstream and downstream of the meter in order to enable maintenance and verification 
of the meter and monitoring of the system. 

Operating conditions 

Temperature class: T30/T50 

Admissible pressure (MAP): 16 bar 

Straight pipes and flow straighteners 

For  the  usage  of  upstream  and/or  downstream  straight  pipes  refer  to  the  letters  U  and  D  marked  on  the  dial.  If  the 
letters U and/or D are followed by the letter S, a flow straightener must be installed. 

Battery 

The battery has a service life of 13 years. It is recommended to replace the battery before it is completely discharged in 
order to avoid malfunction. 