2.0 - TECHNICAL DATA

• Use 

 

: non-aggressive gases of the three families (dry gases)

• Ambient temperature (TS) 

: -20 ÷ +60 °C

• Power voltages (see table 2a - 2b) 

: 12 Vdc - 12 V/50 Hz - 24 Vdc - 24 V/50 Hz - 110 V/50-60 Hz - 230 V/50-60 Hz*

• Power supply tolerance 

: -15% ... +10%

• Electric wiring 

: electric cable l=3 metres with wire terminals

• Absorbed power 

: see table 2a - 2b

• Maximum operating pressure 

: 500 mbar

• Closing time 

: < 1 s

• Protection rating 

: IP65

• Coil protection mode 

: II 3G Ex mc ec nC IIC T4 Gc X  -  II 3D Ex mc tc IIIC T135°C Dc X

• Mechanical resistance 

: Group 2 (according to EN 13611)

• Rp threaded connections 

: (DN 20 - DN 25 - DN 32 - DN 40 - DN 50) according to EN 10226

• Flanged connections to be coupled 
    with PN 16 flanges  

: (DN 25** - DN 32 - DN 40 - DN 50) ISO 7005 / EN 1092-1

• NPT threaded or ANSI flanged connections  : on request
• In compliance with 

: EN 60079-0-7-14-15-18-31 - ATEX Directive 2014/34/EU 

   

 

  EMC Directive 2014/30/EU - LVD Directive 2014/35/EU 

 

 

  

 

 RoHS II Directive 2011/65/EU

*   Only single-phase, the device does not work if powered with three-phase voltage

.

** DN 25 with swivel flanges.

2.1 - MODEL IDENTIFICATION

M16/RMX N.A.  :

 Normally open, manual reset solenoid valves for gas 

ATEX 3G - 3D

MBA/RMX N.A.  : 

Normally open, manual reset solenoid valves for gas, low absorption  ATEX 3G - 3D

3.0 - COMMISSIONING THE DEVICE

  3.1 - OPERATIONS PRIOR TO INSTALLATION

All installation operations must be carried out in the absence of an explosive atmosphere.

• It is necessary to close the gas upstream of the valve prior to installation;
• Make sure that the line pressure 

DOES NOT EXCEED

 the maximum pressure declared on the product label;

• Any protective caps (if any) must be removed prior to installation;
• Valve pipes and insides must be clear of any foreign bodies;

If the device is threaded:
• make sure that the pipe thread is not too long, to prevent damaging the body of the device when screwing it on;
If the device is flanged:
• make sure the inlet and outlet counter-flanges are perfectly coaxial and parallel in order to prevent unnecessary 

mechanical stress to the body. Also calculate the space to insert the seal gasket;

• With regard to tightening operations, equip yourself with one or two calibrated torque wrenches or other controlled 

locking tools;

• The safety regulations on handling loads in force in the country of installation must be complied with. If the device to 

be installed exceeds the weight allowed, suitable mechanical equipment and adequate slings must be used. Necessary 
precautions must be taken during the handling phases so as not to damage/ruin the external surface of the device. 

• In accordance with EN 161 a suitable filter must be installed upstream of a gas closing safety device; 
• With outdoor installation, it is advisable to provide a protective roof to prevent rain from damaging the electrical parts of 

the device.

• Prior to carrying out any electrical wiring operations, make sure that the main voltage matches the supply voltage indicated 

on the product label;

Summary of Contents for M16/RMX N.A.

Page 1: ...ximum operating pressure Pression maximum de fonctionnement Presi n m xima de funcionamiento 0 5 bar Attacchi filettati Threaded connections Raccords filet s Conexiones roscadas DN 20 DN 25 DN 32 DN 4...

Page 2: ...i Drawings Dessins Dise os 31 Dimensioni tabella 1 Dimensions table 1 Dimensions tableau 1 Dimensiones tabla 1 34 Bobine di ricambio tabella 2a 2b 35 Spare coils table 2a 2b Bobines de rechange tablea...

Page 3: ...ne richiamata l attenzione su dettagli tecnici rivolti al personale qualificato PERICOLO In caso di inosservanza oltre a danni a beni materiali possono essere procurati danni alle persone e o animali...

Page 4: ...za di atmosfera esplosiva E necessario chiudere il gas a monte della valvola prima dell installazione Verificare che la pressione di linea NON SIA SUPERIORE alla pressione massima dichiarata sull etic...

Page 5: ...ge siano coerenti con la connessione da assemblare Le guarnizioni devono essere prive di difetti e devono essere centrate tra le flange Se a guarnizioni inserite lo spazio rimanente eccessivo non cerc...

Page 6: ...are periodicamente l integrit del trattamento superficiale dissipativo di bobina e connettore Non installare in ambienti nei quali il prodotto si trovi a diretto contatto con gas corrosivi prodotti ch...

Page 7: ...MANUTENZIONE Tutte le operazioni di manutenzione devono essere eseguite in assenza di atmosfera esplosiva Terminate le operazioni di seguito descritte ripetere le procedure indicate al paragrafo 5 Ne...

Page 8: ...3 VA TS 20 60 C II 3G II 3D year 2017 Lot U1745 25407 00001 Modo di protezione II product group 3 product category Gas II 3G Ex mc ec nC IIC T Gc X G atmosfera esplosiva con gas o vapori Ex idoneo per...

Page 9: ...reset knob 17 is visible 1 2 KEY OF SYMBOLS ATTENTION Attention is drawn to the technical details intended for qualified staff DANGER In the event of inobservance may be caused damages totangiblegood...

Page 10: ...tions must be carried out in the absence of an explosive atmosphere It is necessary to close the gas upstream of the valve prior to installation Make sure that the line pressure DOES NOT EXCEED the ma...

Page 11: ...ree from defects and must be centred between the flanges If after installing the gaskets there is still an excessive space in between do not try to reduce the said gap by excessively tightening the bo...

Page 12: ...d connector Do not install in environments where the product is in direct contact with corrosive gases chemicals salt water water or steam C3 or medium degree of environmental pollution Contact the te...

Page 13: ...turator is open 5 0 FIRST START UP Before start up make sure that all of the instructions on the rating plate including the direction of flow are observed After gradually pressurising the plant check...

Page 14: ...tion in force in the country where this operation is performed 8 0 WARRANTY The warranty conditions agreed with the manufacturer at the time of the supply apply For damage caused by Improper use of th...

Page 15: ...ome additional protective measures to ensure that it remains an inactive source of ignition in case of events expected regularly X particular conditions of use Dust II 3D Ex mc tc IIIC T C Dc X D expl...

Page 16: ...1 2 L GENDE DES SYMBOLES ATTENTION Attire l attention sur les d tails techniques s adressant au personnel qualifi DANGER Le non respect entra ne non seulement des dommages mat riels maisaussidesdomma...

Page 17: ...d atmosph re explosive Il est n cessaire de fermer le gaz en amont de la vanne avant l installation V rifier que la pression de ligne NE D PASSE PAS la pression maximum d clar e sur l tiquette du prod...

Page 18: ...us ou les boulons progressivement selon un sch ma en croix voir l exemple ci dessous Il faut d abord les serrer 30 puis 60 jusqu 100 du couple maximum cf le tableau ci dessous conform ment la norme EN...

Page 19: ...finies dans la directive 99 92 CE Pour d terminer la qualification et l extension des zones dangereuses consulter la norme CEI EN 60079 10 1 S ilestinstall etsoumis l entretienenrespectantpleinementt...

Page 20: ...es courants vagabonds ou toute condition de diff rence de potentiel entre les dispositifs pr sents sur l installation V rifier p riodiquement qu une bonne conduite lectrique subsiste entre le corps de...

Page 21: ...positif et l usure naturelle 9 0 DONN ES DE LA PLAQUE L utilisateur a l obligation de maintenir clairement visible le marquage de la vanne les ventuels rev tements le coating les peintures effectu es...

Page 22: ...ur assurer qu il reste une source d allumage non active en cas d v nements attendus avec r gularit X conditions particuli res d utilisation Poussi res II 3D Ex mc tc IIIC T C Dc X D atmosph re explosi...

Page 23: ...LEYENDA DE S MBOLOS ATENCI N Se llama la atenci n sobre detalles t cnicos dirigidos al personal cualificado PRECAUCI N En caso de incumplimiento adem s de da os en bienes materiales tambi npuedenprovo...

Page 24: ...explosiva Hay que cerrar el gas aguas arriba de la v lvula antes de la instalaci n Compruebe que la presi n de l nea NO SEA SUPERIOR a la presi n m xima declarada en la etiqueta del producto Los posib...

Page 25: ...no deben tener defectos y deben estar centradas entre las bridas Si con las juntas puestas el espacio que queda fuese excesivo no trate de rellenarlo apretando excesivamente los pernos del aparato La...

Page 26: ...se encuentre en contacto directo con gases corrosivos productos qu micos agua salada agua o vapor grado de contaminaci n medioambiental C3 o medio Para cualquier otro uso contacte con la oficina t cn...

Page 27: ...iento es fundamental respetar las normas Ex en concreto la EN 60079 14 La instalaci n el ctrica debe ser realizada por personal autorizado de acuerdo con las normas nacionales pertinentes No instale e...

Page 28: ...3 2 Compruebe la estanqueidad de las conexiones embridadas roscadas en la instalaci n Compruebe la estanqueidad y el funcionamiento de la electrov lvula Limpie regularmente el producto para evitar ac...

Page 29: ...os de garant a ni resarcimiento de da os Adem s se excluyen de la garant a los trabajos de mantenimiento el montaje de aparatos de otros fabricantes la modificaci n del dispositivo y el desgaste natur...

Page 30: ...icionales para garantizar que permanezca una fuente de ignici n no activa en caso de eventos esperados con regularidad X condiciones particulares de uso Polvos II 3D Ex mc tc IIIC T C Dc X D atm sfera...

Page 31: ...31 Madas Technical Manual 3 3 2aX REV 0 of 1st Aug 2019 M16 RMX N A MBA RMX N A IT EN FR ES fig 1 Rp DN 20 Rp DN 25 fig 2 Rp DN 32 Rp DN 40 Rp DN 50...

Page 32: ...32 Madas Technical Manual 3 3 2aX REV 0 of 1st Aug 2019 M16 RMX N A MBA RMX N A ES FR EN IT fig 3 DN 32 FL DN 40 FL DN 50 FL...

Page 33: ...ing 13 Centre pin 14 Green band VPI 15 Pin sealing O Ring 16 Reset knob ES fig 1 2 y 3 1 Manguito bobina 2 Cable de alimentaci n 3 Bobina 4 Tornillo de fijaci n de la bobina 5 Tapa 6 Obturador 7 Arand...

Page 34: ...ttacchi flangiati Flanged connections Raccords brides Conexiones bridadas fori holes trous orificios A B C D E DN 20 DN 25 120 152 94 29 5 122 5 DN 32 DN 40 160 198 140 37 161 DN 50 160 218 140 45 173...

Page 35: ...ines pour lectrovannes MBA RMX N A Bobinas para electrov lvulas MBA RMX N A Voltaggio Voltage Voltage Voltaje Codice bobina Coil code Code de la bobine C digo de la bobina Timbratura bobina Coil stamp...

Page 36: ...d with P1 50 mbar Diagramme calcul avec P1 50 mbar Tabla de p rdidas de carga calculado con P1 50 mbar dv densit relativa all aria dv density relative to the air dv densit relative l air dv densidad r...

Page 37: ...T MEROS DE FKM Viton Aggiungere la lettera V dopo le cifre indicanti gli attacchi Add the letter V after figures denoting the connection Ajouter la lettre V apr s les chiffres indiquant les connexions...

Page 38: ...V 50 Hz RM04X 004 24 Vdc RM04X 005 24 V 50 Hz RM04X 003 110 V 50 60 Hz RM04X 002 230 V 50 60 Hz RM04X 008 DN 32 12 Vdc 2VA RM05X 012 24 Vdc 2VA RM05X 014 12 Vdc RM05X 001 12 V 50 Hz RM05X 004 24 Vdc R...

Page 39: ...50 60 Hz RM25X 008 DN 32 12 Vdc 2VA RM32X 012 24 Vdc 2VA RM32X 014 12 Vdc RM32X 001 12 V 50 Hz RM32X 004 24 Vdc RM32X 005 24 V 50 Hz RM32X 003 110 V 50 60 Hz RM32X 002 230 V 50 60 Hz RM32X 008 DN 40 1...

Page 40: ...3289 Fax 39 0442 27821 http www madas it e mail info madas it Ci riserviamo qualsiasi modifica tecnica e costruttiva We reserve the right to any technical and construction changes Nous nous r servons...

Reviews: