Appendix III
____________________________________________________________________________________________
56 | Installation, Operation & Maintenance Instructions EASYCHLORGEN
Appendix III – Service Log
Date:
System type / model:
Serial number:
Hour meter:
Service Item
OK
Comments
Electrochlorinator
Check Product tank
1)
For Leaks
Check Electrodes for
1)
Scale
2)
Leaks
3)
Correct operation
Check Softener
See Operator Manual
Solenoid Valves
1)
Water Correct operation
2)
Brine Correct operation
3)
Dilution Correct operation
Hydrogen Sensor
1) Correct operation
Brine Tank
1)
Check for leaks and clean tank
Control Panel Check
1)
Terminals for security and signs of over heating
2)
Check all components are present, correctly installed, and
operating correctly
3)
All fuse rating are correct
4)
Correct operation of panel
Ventilation
1)
Check pipe work
2)
Check air flow sensor
3)
Check room ventilation
Complete Operators Log
System Operation / Settings
Hydrogen Sensor (%):
Product Temperature:
Volts:
Amps:
Cycle Time:
Air Flow:
Brine Timer:
Hours Run:
Service Check Sheet