HomeWorks QS Installation Checklist 

This checklist is intended to provide reminders before the installation process begins, as well as when it 
is complete. 

Panel Link 

 

Daisy chain the Module Interfaces (MIs) on each Panel Link 

The MIs must be wired in a daisy chain configuration on the link. The maximum wire run length is 
1,000ft using 18/22 wire (twisted and shielded). 

 

Terminate the MI link 

The MI link must be terminated at the last MI using an LT-1 link terminator (provided in the 
processor box) if the link runs farther than 50 feet. A 120-ohm resistor may be used across terminals 
3 and 4 if an LT-1 isn't available. 

 

Terminal 2 is unused for MIs 

Do not connect terminal 2 between external MIs and the Processor. All external MIs have their own 
integral power supply and do not need to be powered from the Processor. 

 

Install 4R and 4M modules in the bottom locations of a remote power panel 

This is the optimum configuration for heat dissipation, but it is not necessary. 

 

Remove bypass jumpers 

Remove the bypass jumpers from the RPM terminal blocks after verifying the system high-voltage 
wiring. 

 

MI and RPM Addresses 

Make sure that the dial switches on the MI and each RPM matches the appropriate address: 1 
through 8 for RPMs and 0 through F for MIs.  

 

Manual Override Switch 

Wire manual override switch(s) to each MI. 

 

 

 

 

 