Issue 2 December 1996
6-1
6
Customer Acceptance
Project Management Tasks:
This chapter lists the tasks that the Project Manager must perform with the
customer to hand the DEFINITY AUDIX system over to the customer. Most of
these tasks are part of the Streamlined Implementation process. Therefore, they
are not described in this document but are listed here as a final check to make
sure they are completed. These tasks include:
Task 29: Cutting the System into
Service
Changing the call coverage path for subscribers to the DEFINITY AUDIX system
hunt group may depend on the switch in which the DEFINITY AUDIX system is
installed. Therefore, the details are described in
Switch Administration for the
DEFINITY AUDIX System
, 585-300-509.
Task 30: Perform a Walk Through
Perform a walk through with the customer that includes the following:
■
Show the customer the System-Parameters Customer-Options screen to
verify that the purchased ports and features are activated (log in to the
administration terminal as cust to display this screen).
■
Verify that the second blank cartridge tape is present (the first is installed
in the tape drive for system backups).
Summary of Contents for Definity Audix System
Page 14: ...About This Document xiv Issue 2 December 1996...
Page 22: ...Prerequisites 1 8 Issue 2 December 1996...
Page 96: ...Initial System Administration 3 38 Issue 2 December 1996...
Page 170: ...Option Settings B 20 Issue 2 December 1996...