Lucent Technologies 415B Battery Plant for 4ESS
Issue 6 September 1999
Retrofit of 415A Battery Plant 7 - 35
All hardware for making electrical connections to the KS-22089
ac cabinets can be found inside the cabinet. The input ac lugs are
not provided and must be furnished by the line engineer.
Follow local codes and NEC codes and requirements for
connecting the service for the ac cabinets. (Service should be
100 amperes for 480-volts input and 200 amperes for 208 and
240 volts input.)
Six breakers are provided for each cabinet, and Position
14, 16, 18 is a spare in case of a failure. See Figure 7-16.
Figure 7-16: AC Breaker Locations with Spare
Pos 2, 4, 6
Pos 8, 10, 12
Pos 14, 16, 18
(Spare Breaker)
Pos 7, 9, 11
Pos 13, 15, 17
Pos 1, 3, 5