EMERGENCY LIGHTING TESTING

Months 1 to 11 inclusive – Function Test, interrupt the permanent/UnSwitched supply and check the luminaire operates in Emergency 

mode at reduced output

Month 12 (Annual) – As months 1 to 11 but for a full 3 hour duration

Luminaire Ref / Location:

  ........................................

In Case of difficulty, contact the Installation Engineers:- 

Tel: .........................................................

LBM290X11E40

Duration 3 Hours

Lamp Type - LED

INITIAL USE AND ROUTINE TESTING

From initial install the downlight will require up to 24 hours for the batteries to be fully charged and provide the rated 3HR duration in 
Emergency mode. Then following subsequent Emergency use, from full discharge will take approx. 14hrs to fully recharge batteries.

It is important that the luminaire is routinely tested to ensure the batteries are conditioned and also to fully comply with BS5266. 
A function test should be conducted every month with an annual test of the full 3hr duration. Records can be kept on the adjacent table.

It is recommended that batteries are replaced every 4 years to ensure the optimum charging cycle is maintained.  

Month

Test

1

Function

2

Function

3

Function

4

Function

5

Function

6

Function

7

Function

8

Function

9

Function

10

Function

11

Function

Annual

Full Test

Signed

Date

Fifth Year

Signed

Date

Fourth Year

Signed

Date

Third Year

Signed

Date

Second Year

Signed

Date

First Year

WARRANTY    

Products are protected by warranty for a period of 3 year warranty from date of purchase against defects in material and workmanship 

(unless otherwise stated). Should a product fail to perform as described within the warranty period it will be repaired or replaced with 

the same or equivalent product by Luceco, free of charge provided that you: (1) return the product to us with shipping charge prepaid, 

(2) provide us with proof of the original date of purchase and (3) quote our return authorization number

Repaired or replaced products will be returned to you with shipping charges prepaid. Replacement products may be refurbished 

or contain refurbished materials. If in our sole discretion, we are unable to repair or replace a defective product, we will refund the 

purchase price of the product

This warranty will not apply if in our judgment, the product fails due to damage in shipment, handling, storage, accident, abuse or 

misuse, or if it has been used in a manner not conforming to our product instructions, has been modified in any way, or has any serial 

number removed or defaced. Repair or attempted repair will void this warranty. Our maximum liability under the terms of this warranty 

is limited to the purchase price of the product covered by the warranty

The warranty is given under English Law. If any part of this warranty is deemed unenforceable (including any provision in which we 

exclude our liability to you) the enforceability of any other parts of the warranty will not be affected. These terms do not reduce your 

statutory rights

THESE TERMS AND CONDITIONS ARE SUBJECT TO CHANGE WITHOUT PRIOR NOTICE

For further details, terms and conditions and online registration please see 

www.luceco.co

SUGGESTED METHOD OF INSTALLATION

The bulkhead is designed for mounting in any of the  

following options: – 

•  Surface Wall Mounting

•  Surface Ceiling Mounting 

1.  Surface mounted options may use rear cable entry for flush 

mounting or there is facility for surface Conduit ‘besa’ box 

mounting or side conduit entry. (Image 1)

2.  With the method of mounting chosen, remove the front 

Diffuser, by undoing the three front Screws. (Image 2)

3.  To remove LED tray, loosen two retaining screws,  

and twist tray clockwise and remove. (Image 3)

4.  This Bulkhead can be mounted on ceilings and vertical walls. 

Ensure the mounting surface is suitable for installation. 

Once mounting points are decided, drill out mounting holes 

and any cable entry points needed.

5.  Cable Entry Points must be drilled out with a 20mm bit, 

cleaned of any loose burrs and fitted with a suitable  

IP65 gland, if the IP65 rating is to be maintained.  

Otherwise the IP rating would be reduced.

Tech Help Line

UK -

 0845 194 7584

Non UK -

 +44 (0)1952 238 100

Visit our website at

Luceco is a registered trade mark of Nexus Industries Ltd.

Supplied by

BG Electrical Ltd

Stafford Park 1 TF3 3BD ENGLAND

www.luceco.co

LED

 IP65

Mosi Emergency Bulkhead

PART CODE: LBM290W11E40, LBM290B11E40

Installation & Operating Instructions

SPECIFICATIONS

• 

Suitable for use with Mains voltage of 220-240V AC

• 

This product must be disconnected before insulation  

 

 

resistance testing of the lighting circuit

• 

Check for electrical cables and pipes before installation

NOTE

 – To comply with regulations, installation must be carried 

out by qualified electrician and in accordance with the current IEE 
Wiring Regulations (BS7671) and Building Regulations.

ENSURE ELECTRICAL SUPPLY IS DISCONNECTED/ISOLATED 
BEFORE COMMENCING INSTALLATION

• 

To maintain the IP65 rating of the bulkhead, a suitable 20mm  

 

cable gland should be used in conjunction with rubber  

 

 

insulated cable to ensure the supply cable is sealed in the   

 

gland. Failure to use a gland and/or rubber insulated cable  

 

may result in water ingress

 

Page 1

4

1

cable entry 

points

cable entry 

points

2

loosen 

screws here

3

loosen 

screws here

3HR

EMERGENCY

CRI

   80

>

IP65

RATED

  3

GUARANTEE

year

Reviews: