P A D - C L I M A T E - S Y S T E M
Assembly instruction and operators manual
Assembly
14
3.7.4. Top Bracket
Measure off the place for the Top Bracket above the
Supply Unit. Masure off the place for the top Bracket
at the end(s). Then mark with a chalk line the horizon-
tal connection between this points. Fasten the Top
Brackets in the distance from max 75 cm (30 in). Fas-
ten each Top Bracket with two fasteners and washers.
3.7.5. Supply Unit
Build the piping between the Supply Unit and the Water Distribution Pipe.
Pay attention to straight cuts of the pipe! Subsequent-
ly, belve and if necessary clean the front of the pipes.
Contamination or splinters in the tubing system can
reduce the efficiency of the system or cause damage!
Cut and stick together the whole piping system from the pump to the sump. Place the
Pump Cover on the Supply Unit for preventing dirt and splashing water to the Pump.
Consider the arrangement of the construction units as down in the sketch.
Fasten the float valve in the housing. The water connecting
should take place at a later time, so that the
system
is not
filled inadvertently.