Preparing the Installation
11
1.4 Selecting and Preparing a Site for Installation
When selecting an installation location consider the following points:
•
The inverter must be installed on a
wall that can support the inverter’s weight.
•
The location must be free from vibration. Vibration can adversely affect the operation of
the inverter.
•
The inverter can become very hot during operation. Install the inverter on a surface that
is fire-resistant or flame-retardant and with sufficient clearance around the inverter to
allow air to circulate. The illustrations below detail the required installation clearances.
Summary of Contents for H100 0008-2(PLUS)
Page 26: ......
Page 30: ...Preparing the Installation 4 37 90 kW 3 Phase ...
Page 31: ...Preparing the Installation 5 110 132 kW 3 Phase ...
Page 32: ...Preparing the Installation 6 160 185 kW 3 Phase ...
Page 33: ...Preparing the Installation 7 220 250 kW 3 Phase ...
Page 34: ...Preparing the Installation 8 315 400 kW 3 Phase ...
Page 35: ...Preparing the Installation 9 500 kW 3 Phase ...
Page 46: ...Installing the Inverter 20 200 V 0 75 18 5kW 400 V 0 75 185kW 400 V 220 500kW ...
Page 48: ...Installing the Inverter 22 ...
Page 63: ...37 Installing the Inverter Input and Output Control Terminal Block Wiring Diagram ...
Page 207: ...Technical Specification 181 6 3 External Dimensions 0 75 30 kW 3 phase 37 90 kW 3 phase ...
Page 208: ...Technical Specification 182 110 185 kW 3 phase 220 500 kW 3 phase ...
Page 237: ...211 목차 EN IEC 61800 3 2018 EN 61800 5 1 2007 A1 2017 ...
Page 238: ...212 ...
Page 239: ...213 목차 ...