S35
Pre-Installation and Site Preparation Guide
Page 18 of 52
Loring Smart Roast Proprietary – This document is controlled by
Document Control. By printing this document, it will become a “Reference” copy.
Users are responsible for verifying that it is the latest revision available.
1006705 Rev B
Overhead Clearances – S35 Roaster
Overhead clearance should accommodate the roaster plus a minimum stack height.
This clearance is also necessary for routine maintenance, as well as providing room to
maneuver during installation.
Minimum Total Ceiling Height: 118" (300 cm)
Clearance:
12"
(31 cm)
Height:
106"
(270 cm)