Chapter 3: Procedures
3-9
HYDROBAR EXPRESS 220
Front Rest Alignment
This procedure is used to align the front rest. This procedure requires special tooling. To receive this tooling, contact LNS America, Inc
at 513-528-5674. Some bar feed parts were removed for clarity of the pictures for this procedure.
Tools List:
•
10mm
combination
wrench
•
13mm
combination
wrench
•
3mm hex key
•
4mm hex key
•
5mm hex key
•
Rest alignment tooling (loaned from LNS factory)
Procedure
Conditions:
•
Main guiding channel open
•
No bar stock in the channel
•
Main bar feed power off
Step 1: Remove the three guiding channels closest to the front rest.
Alignment tube
Alignment bar
45mm alignment
bushing
75mm alignment
bushing
Alignment blocks
Tube alignment
bushing
Remove guiding
channels
Step 2: Remove the front rest cover by loosening the four thumb screws (two on either side of the cover).
ws
Thumb scre
Summary of Contents for Hydrobar Express 220
Page 61: ......
Page 143: ......
Page 147: ......
Page 156: ...Chapter 6 Spare Parts 6 9 HYDROBAR EXPRESS 220 Servo Motor Assembly ...
Page 161: ...6 14 Chapter 6 Spare Parts HYDROBAR EXPRESS 220 Hydraulic Pump Assembly ...
Page 163: ...6 16 Chapter 6 Spare Parts HYDROBAR EXPRESS 220 Diameter Adjustment Motor Assembly ...
Page 164: ...Chapter 6 Spare Parts 6 17 HYDROBAR EXPRESS 220 Air Regulator and Cable Passage Plate ...