Preparation for use
4.2. Storing the machine
Pack the machine in plastic film for storage.
Only store the machine in an indoor space with a dry environment.
4.3. Installation and assembly
The machine must only be installed in an indoor space, which meets the
following conditions:
Fortified, level floor with a load carrying capacity of at least 2.5 t
Temperature range +10° to +40°C
Humidity: 5 – 95 % (not condensing)
4.3.1. Installing machine
Fasten lifting equipment to the four connection points on the steel
carriers
(35)
or lift with a forklift under the two lower beams
(37)
.
Remove the packaging from the machine.
Adjust the machine feet
(6)
until the machine is horizontally level.
4.3.2. Connecting the machine electrically
DANGER
High voltage
Death or injury from electric shock
Make sure that the main switch
(11)
is in the »Off« position.
Connect the machine to the power supply
(12)
.
Place the main switch
(11)
on the back of the machine into the "On"
position.
Ensure that both »EMERGENCY STOP«
buttons (10)
and
(17)
are
disengaged.
The machine is ready for operation.
The machine is delivered ready for connection to a right-hand power supply.
A phase monitor checks the connection regarding the correct phase
sequence. If the phase sequence is incorrect the LED "Incorrect phase
sequence"
(19)
lights up, and the machine cannot be turned on. Use a
connection cable with phase inverter for easier power connection with the
correct phase sequence.
24
Deslagging machine SBM-M 1000/1500 D2