Problem
Possible Cause
Corrective Action
Node
Nodes not connecting (i.e.
the “Node Connected” box
does not count up when
the irrigator safety line is
powered up)
Node power supply is not
properly connected
Check the node power supply con-
nection according to the “Installing the
Power Supply” section of this manual
Node not connecting
Power cable incorrectly
connected to the node
Check the node power supply con-
nection according to the “Installing the
Power Supply” section of this manual
DIP switch setting are
incorrect
All DIP switches should be set the same
on every PCB. Except for the GPS node
which should have the GPS setting (DIP
switch “GPS”) to “ON”
MAC address is incorrect
Open the node enclosure and record
the MAC address written on the PCB.
Make sure both lines of the MAC ad-
dress on the sticker are programmed in.
Open FieldMAP and compare the MAC
address of the faulty node to what’s
displayed for the same node location in
Field Map . If different, update the plan
and upload it to the VRI control.
Node driver chip is defec-
tive
Node driver chip is defective, replace
node board. The new MAC address of
the replacement board will need to be
programmed in the VRI main control.
Valve
A single valve is not puls-
ing but the valve is ticking
The sprinkler nozzle is
blocked
Check for a blocked sprinkler head
The valve is blocked
Disassemble the valve and remove any
matter that may be blocking the valve
Ruptured diaphragm.
Replace the diaphragm.
Spring inside stainless
steel solenoid sleeve
interferes with the plunger
seating. Therefore, the
magnet does not engage.
Check for obstructions blocking the
spring and remove any debris.
Replace the spring.
A single valve is not puls-
ing and the valve is not
ticking
The valve plunger is
jammed
Disassemble the valve and check to see
if the plunger is jammed.
Valve solenoid is open
Replace solenoid
Faulty valve plug terminal
connection
Disassemble the valve plug and check
that the terminals are all connected
Loose wiring or wire not
connected
Check wire terminals on the valve and
node board
Troubleshooting
Summary of Contents for GROWSMART
Page 1: ...Variable Rate Irrigation Installation Manual P N 1600043 Rev M ECN 34095...
Page 2: ......
Page 4: ...P N 1600043 Rev M ECN 34095 VRI Installation Manual...
Page 27: ...P N 1600043 Rev M ECN 34095 13 VRI Installation Manual This page is left blank intentionally...
Page 30: ...P N 1600043 Rev M ECN 34095 16 VRI Installation Manual VRI VISION BOSS Control Panel Wiring...
Page 44: ...P N 1600043 Rev M ECN 34095 30 VRI Installation Manual...