3 June 2022
Page | 20
Stainless Steel Base Plate Installation
Follow the same procedure for both non-cable management and cable-management pedestals.
When pouring new concrete, purchase a breezEV Wet Concrete Pedestal Anchor Kit (
EVC-L2-ACC-ANCHOR KIT WET)
1.
Using the provided template, set the 4 J-bolts in place (see below for template).
2.
Ensure that at least 40in of wire extends out of the conduit.
3.
Let concrete set.
When installing on existing concrete, hardware Is provided.
1.
Using the provided template, mark the position of the 4 bolts (see below for template).
2.
Ensure that at least 40in of wire extends out of the conduit.
3.
Drill the 4 holes in the concrete, each minimum 2.2” deep.
4.
Install the anchor bolts, through the base plate, with washers. Bolts must be a minimum of 2.25” above the
concrete pad.
Attaching the Pedestal Lower Section to the base plate.
1.
Attach 3-sided sheet metal to the base plate using 8 x T27 screws with washers
Summary of Contents for breezEV EVC-L2-D Series
Page 7: ...3 June 2022 Page 7 SPECIFICATIONS ...
Page 8: ...3 June 2022 Page 8 DIMENSIONS CHARGER ...
Page 9: ...3 June 2022 Page 9 NON CABLE MANGAGEMENT PEDESTAL ...
Page 10: ...3 June 2022 Page 10 CABLE MANGAGEMENT PEDESTAL ...
Page 13: ...3 June 2022 Page 13 WALL MOUNT INSTALLATION Mechanical Installation ...
Page 18: ...3 June 2022 Page 18 ...
Page 21: ...3 June 2022 Page 21 ...
Page 29: ...3 June 2022 Page 29 STATUS DESCRIPTIONS ON CHARGER Normal ...