Regulator PFCL Elite

 

Quick guide PFCL Elite 

REACTIVE ENERGY REGULATOR  

PFCL Elite

 

               

 

1.-  Principal functions 

-  Cos 

φ

 regulator      

   Capacitor connection (6 or 12 steps)

 

-  Network analyzer   

   Measurement of electrical parameters

 

-  Alarm manager      

    Display and automatic solution

 

 

 
This manual  is  intended as a  rapid guide to the use  and operation  of  the  PFCL  Elite 
regulator. 

 

 

Any  manipulation  or  use  of  the  equipment  different  from  that  specified  by  the 
manufacturer  may  compromise  user  safety

.  The  apparatus  must  be  disconnected 

from the power supply before carrying out any maintenance operation. In the event of 
failure  in  the  operation  or  the  protections,  the  unit  must  be  left  out  of  service  and  its 
reconnection must be prevented until the problem has been corrected.

 

 

2.-  Connections 

A current transformer must be installed for the start-up (I

n

 / 5 A) depending on the 

total current of the load. 

The  regulator  power  supply voltage  will  be  two-phase,  preferably  L1  for  U

L1

  and 

L2 for U

L2

 , and the current will preferably be taken from L1. It must be supplied by 

means of  an  automatic switch. See  cable section  and  protections  in the  table  of 
technical features. 

 

 

 

The current transformer must be placed in such 
a way that it measures the total current of the 
loads plus the capacitors. 

The transformer for the leakage current must be 
placed so that it measures the current in the 
capacitor bank and must include lines L1, L2, L3 
and N. 

 

 

The unit has a switched relay exclusively for the alarm outlet. 

  

 

 

 

 2.1.- Communications 

 

The PFCL Elite regulators can be connected to a computer or another unit by 
means of the standard RS-485 bus included. This system is able to focus data 
on a single registry point (Power Studio® System). 
 
In a network of equipment, the PFCL Elite communicates by question-answer 
(slave). 
 
The  PFCL  Elite  communicates  with  the  MODBUS  RTU©  protocol,  which 
enables  it  to  access  the  electrical  parameter  and  the  main  variables  and 
configurations. Contact the manufacturer for the table of addresses.  
 
See section 4.3. to change the communications configuration. 
 

 

3.-  Technical features 

 

 

Main power supply and voltage 
measurement. 

480, 400, 230, or 110 Vac. +15 % -10 %; 50 / 60 Hz, (see label) 
Power supply: 

U

L1

-

 U

L2

. Measurement 

U

L1

,

 U

L2

U

L3

 y 

U

N

 

Power supply cables  

Section 1.5 mm

2

 , gl 0.5 to 2 A protection fuse  

Current measurement circuit 

Current transformer, 

I

n

 /5 A AC., preferably on phase L1. Min. 

cable section. 2.5 mm

2

 

Leakage current measurement 
circuit 

Nominal secondary transf. current: 

I

sec = 2 mA AC. 

Transformer with ratio of 500: 

I

 = 1 A AC.  +20% 

Current measurement margin 

Current 

I

: 0.05 to 5 A AC. (maximum ov20 %) 

Leakage current 

I

: 0.01...1 A AC. (maximum ov20 %) 

Measurement accuracy 

Voltage and current: 1 %;  cos 

ϕ

:  2 % 

±

  1 digit 

Temperature measurement 

Approx. external temperature. Range: 0...80 ºC. Accuracy: 

±

 3 ºC 

Consumption 

8.2 VA (empty) ; 9.3 VA (6 relays); 11 VA (12 relays) 

Output 

Relays. Contacts for 

U

max. 250 Vac., 4 A AC., AC1.  

Cabling and output relay 
protection 

Cable section 1.5 mm

2

 , protection with circuit breaker (C curve) 

of 6 A or gl 6 A fuse 

Alarm relay 

Switched relay for use exclusively for the alarms 

Standards 

IEC 62053-23 (2003-01) Ed. 1.0  
IEC 61326-1, EN61010-1  
UL 508  

 

 

Safety /Insulation 

Category III, Class II , according to EN 61010-1 

Protection degree  

IP40 (equipment mounted, cabinet front panel)

 

IP30 (equipment not mounted) according to EN-60529 

Admissible environmental 
conditions 

Temperature: -20...+60 ºC; Relative humidity: max. 95 % 
(without condensation). Max. altitude: 2000 m 

Control system  

FCP (a programme that minimises the number of operations) 

Communications 

 

Interface: RS-485.     Protocol MODBUS.  
Speed: 9600, 19200, 38400 

The PFCL Elite regulator 
measures and operates in 4 
quadrants according to the 
attached diagram.

 

 

 

90º

180º

-90º

Potencia Consumida

Potencia Generada

Inductivo

KW +
kVAr +
Cos   +

ϕ

Capacitivo

KW -
kVAr -
Cos   -

ϕ

Capacitivo

KW +
kVAr -
Cos   +

ϕ

Inductivo

KW -
kVAr +
Cos   -

ϕ

          Only for 
PFCL Elite 12 steps 

 PFCL Elite 

Reviews: