Installation
44
2.8.1. First-time Start-up of a Parallel System
IMPORTANT
Do not start the UPS until after the installation is finished, the system is commissioned by an
authorized
engineer, and the external input circuit breakers are closed.
CAUTION
Starting the UPS applies mains/utility power to the output terminals. Make sure that the load power is safe and ready to
accept power. If the load is not ready, isolate the load with the output terminal.
The “Parallel” parameters for each UPS in the system must be set and synchronized at first start-up.
To start and set parameters for the parallel system:
1. Make sure that the output CBs of all units in the parallel system are open (off), then close (turn on) the input
CB on each UPS. Each UPS powers on, a self-check screen displays, and the alarm/run indicators are lit for
about 5 seconds.
2. Wait about 30 seconds to allow the rectifier start-up to finish, then at each UPS, set the parallel parameters
as follows:
• If the “System parallel settings async” Alarm displays, clear it and proceed. Communication should not
fail after the parallel settings are synchronized
•
On the display, press
Enter
to display the Main Menu, then use the arrow buttons to select Settings, and
press
Enter
.
• To adjust the settings, you must enter a password. See
Editing Display and Operation Settings
, for details on entering the password and editing the setting parameters.
•
Use the arrow buttons to select the Parallel tab, then press
Enter
to display the parameters list.
•
Select and Enter each parameter setting, and then use last item in the list, Sync parallel parameters, to
validate the settings. For a full description of UPS display functions and settings, see
•
After confirming the parallel parameters and each UPS is operating normally, commission the parallel system,
see
Commissioning Parallel System
below.
Summary of Contents for Vertiv GXT5
Page 1: ...VertivTM Liebert GXT5 UPS 230 V Input 230 V Output Installer User Guide ...
Page 8: ...Important Safety Information 2 This page is intentionally left blank ...
Page 30: ...GXT5 Description 24 This page is intentionally left blank ...
Page 56: ...Operating the UPS 48 Start up Guidance 1 4 Start up Guidance 2 4 Start up Guidance 3 4 ...
Page 60: ... 52 This page is intentionally left blank ...
Page 88: ...Operation and Display Panel 80 This page is intentionally left blank ...
Page 108: ...Maintenance 100 This page is intentionally left blank ...
Page 112: ...Troubleshooting 104 This page is intentionally left blank ...
Page 132: ...Specifications 124 This page is intentionally left blank ...