Check Points
1. One PRIB should be installed on one of the slot No. 1-7 except the slot No.8 and EKSU. It is
recommended that the board is installed in the right slot of BKSU.
2. PLLU or PLLU2(issue 3 or later) MUST be installed on MPB.
3. For QSIG operation, check the mode setting method and the contact assignments of RJ45 type
connector according to the mode of line , TE or NT.
See the clause 3.5.
4. For QSIG operation, SMEMU MUST be required on MPB for QSIG operation.
See SMEMU in
section 2.
5. The clock control cable should be connected to the proper position when multi-ISDN cards are
installed in a system.
See section 3.5.
3.4.6.4 E1IB Installation
E1IB provides an E1 (2.048Mbps) line interface with Pulse and DTMF signaling, but not R2 MFC signaling.
It can be optionally equipped with 3 CPTUs to monitor call progress signals. For using this board, the PLLU
or PLLU2 (issue 3) board should be installed on the MPB. If required, install the CPTU, on the E1IB as
shown in Figure 3.4.6.4.
It is designed to comply with the special national specification and application, so it may not
suitable for the other national specification and/or application.
Function of LED
Status
No
Function
ON
OFF
Remark
LED1
PLL Synchronization
Sync. Error
Normal
LED2
Loss Of Signal from the Line
LOS
Normal
LED3 AIS
Alarm
error
Normal
LED4
Frame Alignment Error
FA error
Normal
LED5
Multi-frame Error
MF error
Normal
LED6
Board Sync Error
Error
Normal
LED7
The status of the line
In use
All channel idle
!
Note
1. All LEDs will be the status of OFF when normal operation.
2. When E1 line is plugged out, LED 2,4 and 5 will be ON.
Function of various connectors
Connector
Function
Remark
CON1
Serial interface connector( 4pin)
Note 1
CON2
RJ45 modular type connector for E1 Line connection
Clause 3.5
CON3
BNC type 75 ohm connector for TX
Note 2
CON4
BNC type 75 ohm connector for RX
Note 2
CON5
Clock control IN for clock daisy chain
Note 3
CON6
Clock control OUT for clock daisy chain
Note 3