Mount and Secure the Express 250
1.
While the Express 250 is elevated, use a 24 mm (15/16 in) hex wrench to remove the bolts and
wooden stands from the bottom of the charging station.
2.
Lift the Express 250 over the mounting bolts on the installation pad, ensuring the bolts align
with the corresponding holes in the bottom of the Express 250. Move the service wiring out of
the way to ensure it is not pinched or trapped.
3.
Lower the Express 250 onto the anchor
bolts.
Note:
The Express 250 should rest on
the leveling nuts and washers, not on
the rails (a). The purpose of the rails is
to ensure the Express 250 is installed a
minimum height from the concrete,
allowing the front and rear panels to sit
flush with the concrete surface.
4.
Install a washer and nut onto each of
the four corner mounting bolts to
secure the Express 250. For easier
leveling, leave a 6.4 mm (1/4 in) gap
between the bottom of these top nuts
and the baseplate of the frame.
5.
Remove the lifting equipment from
the installation area.
6.
Using a level on all four sides, adjust
three of the bottom corner leveling
nuts as needed to ensure that the
Express 250 is both horizontally and
vertically level.
7.
When level, tighten leveling top nuts
by hand. Then raise the remaining
(non-leveling) lower nut by hand-
turning until flush against the Express
250’s frame.
6.4 mm (1/4 in)
250_IGcombo.pdf 20