Mounting the installation backplane
Arrangement of the devices
4
43
EDK94PNE36 DE/EN/FR/ES/IT 2.0
4.2
Arrangement of the devices
SSP94PN200
Fig.11-1
Arrangement concept
The technical data must be taken into account when planning and dimensioning a DC-bus
interconnection.
Arrange the devices as follows for operation in DC-bus interconnection via the DC busbars:
ƒ
Mount the devices side by side from the left to the right.
ƒ
Install the supplying device on the left side:
– DC power supply module (in a first row),
– DC feeding point (in following rows).
ƒ
Install the Multi Drive axis controllers from left to right with decreasing powers.
ƒ
Single Drive axis controllers can be integrated to increase the braking power. These
axis controllers must be equipped with the optional busbar set (E94AZJAxxx).