Commissioning
Before switching on
7
167
EDK82EV903 DE/EN/FR 5.1
7
Commissioning
7.1
Before switching on
Stop!
Special commissioning procedure after long−term storage
If controllers are stored for more than two years, the insulation resistance of
the electrolyte may have changed.
Possible consequences:
ƒ
During initial switch−on, the DC−bus capacitors and hence the controller are
damaged.
Protective measures:
ƒ
Form the DC−bus capacitors prior to commissioning. Instructions can be
found on the Internet (www.Lenze.com).
Note!
ƒ
Do not change the switch−on sequence.
ƒ
In the event of a fault during commissioning please see the chapter
"Troubleshooting and fault elimination".
In order to avoid personal injuries or material damage, check the following before
connecting the mains voltage:
ƒ
The wiring for completeness, short circuit, and earth fault
ƒ
The "emergency stop" function of the system
ƒ
The motor circuit configuration (star/delta) must be adapted to the output voltage
of the controller.
ƒ
If no function module is used, the FIF cover has to be fitted (delivery status).
ƒ
If the internal voltage source X3/20, e.g. of the standard I/O is used, terminals X3/7
and X3/39 have to be bridged.
Summary of Contents for 8200 vector E82CV153K4B
Page 3: ...E82EV153K4B E82EV303K4B 8200vec292 E82EV453K4B E82EV553K4B 8200vec311...
Page 285: ......
Page 286: ...E82EV753K4B E82EV903K4B 8200vec312...
Page 287: ......