Step 2. Tighten screw 1 and 2:
a. Partially tighten screw 1.
b. Fully tighten screw 2.
c. Fully tighten screw 1.
Figure 45. Heat sink installation
Step 3. Tighten screw 3 and 4:
a. Partially tighten screw 3.
b. Fully tighten screw 4.
c. Fully tighten screw 3.
After you install the heat sink, complete the following steps:
1. Install the top cover onto the server (see
“Install the top cover” on page 54
).
2. Install the server into the rack if necessary.
3. Reconnect power cords and all external cables.
Install the air baffle
Use this information to install the air baffle.
Before you install the air baffle, complete the following steps:
1. Read
“Installation Guidelines” on page 32
to ensure that you work safely.
.
53
Summary of Contents for ThinkSystem SR150
Page 1: ...ThinkSystem SR150 Setup Guide Machine Type 7Y54 ...
Page 4: ...ii ThinkSystem SR150 Setup Guide ...
Page 8: ...vi ThinkSystem SR150 Setup Guide ...
Page 25: ...Chapter 2 Server components 17 ...
Page 38: ...30 ThinkSystem SR150 Setup Guide ...
Page 66: ...58 ThinkSystem SR150 Setup Guide ...
Page 86: ...78 ThinkSystem SR150 Setup Guide ...
Page 89: ......
Page 90: ...Part Number SP47A31795 Printed in Chinese Mainland 1P P N SP47A31795 1PSP47A31795 ...