Installation
12.1 For further information see the installation, operating and maintenance manual: IOM
12.2 Preliminary procedures
The machine left the factory in perfect conditions, however when receiving the unit verify its integrity. Immediately report any damage to
the carrier and write it down on the Delivery Note before signing it.
LENNOX or its commercial reference must be promptly notified regarding the extent and type of damage. The Customer must submit a
written report describing any significant damage.
Lifting and transport
While the unit is being unloaded and positioned, utmost care must be taken to avoid abrupt or violent manoeuvres. Be very careful
when transporting it inside rooms. Do not use the unit components as anchors.
The unit should be lifted with Ø1½” GAS steel pipes at least 3 mm thick. Insert them, on the base side members (see fig. below), into
the holes marked with stickers. The pipes, which should protrude by at least 300 mm from all sides, must be secured with ropes of
equal length to the lifting hook (provide stops at the ends of the pipes to prevent the ropes from slipping off because of the weight).
Use ropes or belts long enough to extend beyond the height of the machine. Place spacer bars and boards on top of the unit to avoid
damaging the sides and the top of the unit.
Warning: During all lifting operations make sure the unit is firmly anchored, to prevent it from tilting or
falling.