Step 4. FIELD WIRING

Caution:  Label all wires prior to disconnection 

when servicing controls.  Wiring errors can 

cause  improper  and  dangerous  operation.  

Verify proper operation after servicing.

Refer to Section A for millivolt appliances and 

Section  B  for  electronic  appliances.  The  gas 

valve is set in place and pre-wired at the factory 

on both models.

A. Millivolt Wiring 

(See Figure 35)

 

 

1.

 Appliance-mounted ON/OFF burner control 

switch (rocker switch) is factory installed 

in  the  control  compartment.  An  optional 

wall-mounted  switch, wall thermostat, or 

one of the optional remote control kits may 

also be used. 

2

.  If  a  wall-mounted  ON/OFF  control  or  ther-

mostat is selected mount it in a convenient 

location on a wall near the fireplace.

.  Wire the control switch within the millivolt 

control circuit  using the 15 feet of 2 conductor 

wire supplied with the unit.

Note: The supplied 15 feet of 2 conductor wire 

has one end of each conductor connected to 

the gas valve circuit and the other end of each 

conductor  placed  loose  inside  the  bottom 

compartment.

Caution:  Do Not connect the optional wall 

switch to a 120V power supply.

4. 

If an optional control switch is installed, turn 

the appliance-mounted ON/OFF burner control 

switch to the OFF position.

ELECTRONIC 

WIRING DIAGRAM 

JUNCTION BOX 

BLK 

120 V. 

24 V. 

TRANSF 

ELECTRONIC IGNITION 

CONTROL BOARD 

*WALL MOUNTED ON/OFF SWITCH (OPTIONAL) 

OR REMOTE CONTROL RECEIVER 

APPLIANCE MOUNTED 

ON/OFF SWITCH 

PILOT BURNER 

IGNITER-SENSOR 

ASSEMBLY 

GAS VALVE 

EV2 

EV1 

GROUND 

CONNECTOR 

GREEN LED 

WHITE (6) 

) 0 2 (   

E T I 

H W 

) 0 2 ( 

  E G 

N A R 

BLACK (20) 

) 9 (   

E L P 

R U P 

) 2 1 ( 

  N E 

E R 

BLUE (20) 

BLACK (16) 

WHITE 

FIELD  WIRED 

FACTORY  WIRED 

*Turn The Appliance-Mounted ON/OFF Burner Control Switch 

To The OFF Position If An Optional Control Switch Is Installed 

Optional 

Blower 

Ground 

Figure 35

Figure 36

B. Electronic Wiring  (See

 Figure 36) 

– 

Note: The electronic appliance must be con-

nected to the main power supply.

1

. Route  a  3-wire  120VAC  60Hz  1ph  power 

supply to the appliance junction box.

2

. Remove the electrical inlet cover plate from 

the side of the unit by removing the plate's 

securing screws. 

See Figure 11A on Page 

10.

.  Remove the  cover plate's knockout and then 

feed the power supply wire through the knock-

out opening and into the unit junction box.

4

. Connect the black power supply wire to the 

red pigtail lead

 and the white power supply 

wire to the 

common 

terminal of the outlet 

as shown in 

Figures 36 and 37.

 

5

Connect the ground supply wire to the pig-

tail lead attached to outlet's green ground 

screw.

6

. Appliance-mounted ON/OFF burner control 

switch (rocker switch) is factory installed 

behind the bottom panel. 

  Optional wall-mounted  switch, wall thermo-

stat, or one of the optional remote control 

kits may also be used.  

7.

 If wall-mounted ON/OFF control or thermo-

stat is to be used, mount it in a convenient 

location on a wall near the fireplace.

8.

 If an optional wall-mounted control is to be 

used, wire it  in the low voltage circuit as 

shown in 

Figure 36

.

Note: The supplied 15 feet of 2 conductor wire 

has one end of each conductor connected to 

the gas valve circuit and the other end of each 

conductor  placed  loose  inside  the  bottom 

compartment.

9. 

If  an  optional  control  switch  is  installed, 

turn the appliance-mounted ON/OFF burner 

control switch to the OFF position.

10.

 After  the  wiring  is  complete,  replace  the 

cover plate.

OPTIONAL BLOWER KIT 

(millivolt models only)

If the blower kit is to be installed at the time of 

installation or at a later date, the main power supply 

and wall switch must be installed at the time of 

installation.  

This will require that the electrical 

connections must be made BEFORE the fireplace 

is framed and enclosed in the finished walls.

  

Route a 3-wire, 120 VAC, 60 Hz, 1 ph power 

supply and connect to electrical receptacle wires 

and wall switch or wall rheostat.

TP-TH

TP

TH

APPLIANCE- MOUNTED

ON/OFF SWITCH

BK/W(1)

BK/W(1)

WALL-MOUNTED ON/OFF SWITCH (OPTIONAL)

THERMOSTAT (OPTIONAL)

JUNCTION BOx

BLACK

W

GR

120 

V

AC

WALL MOUNTED CONFIGURATION FOR FAN SWITCH (OPTIONAL)

BK

R

WIRING DIAGRAM MILLIVOLT GAS VALVES

THERMOPILE

GAS VALVE

FAN

(OPTIONAL)

       

CAUTION

Ground supply lead must be con-

nected to the wire attached to the 

green ground screw located on the  

outlet box.  See 

Figure 37

. Failure to 

do so will result in a potential  safety 

hazard.    The  appliance  must  be 

electrically grounded in accordance 

with local codes or, in the absence of 

local codes, the National Electrical 

Code, ANSI/NFPA 70-latest edition. 

(In Canada, the current CSA C22-1 

Canadian Electrical Code).

Summary of Contents for Adagio ADAGIO-EN

Page 1: ...rating plate This appliance is not convertible for use with other gases unless a certified kit is used Adagio Series US P N 850 044M Rev D 06 2008 In the Commonwealth of Massachusetts Installation must be performed by a licensed plumber or gas fitter See Table of Contents for location of additional Commonwealth of Massachusetts requirements Millivolt Models Electronic Model ADAGIO MN ADAGIO EN ADA...

Page 2: ...iances Millivolt appliances are designed to operate on natural or propane gas A millivolt gas control valve with piezo ignition system provides safe efficient operation External electrical power is required to operate the optional blower if installed in these units Electronicappliancesaredesignedtooperateon natural or propane gas An electronic intermit tent pilot ignition system provides safe effi...

Page 3: ...ea Level To High Altitude All Models These appliances are tested and approved for installationatelevationsof0 4500feet 0 1372 meters above sea level using the standard burner orifice See Table 5 For elevations above 4500 feet contact your gas supplier or qualified service technician Install the appliance according to the regulations of the local authorities having jurisdiction and in the USA the N...

Page 4: ...or with an alarm shall be installed Approved Carbon Monoxide Detectors Each carbon monoxide detector as required in accordance with the above provisions shall comply with NFPA 720 and be ANSI UL 2034 listed and IAS certified Signage A metal or plastic identification plate shall be permanently mounted to the exterior of the building at a minimum height of eight 8 feet abovegradedirectlyinlinewithth...

Page 5: ...2 1 latest edition MANUFACTURED HOME REQUIREMENTS This appliance may be installed in an after market permanently located manufactured home USA only or mobile home where not prohibited by local codes Cet appareil peut être installé dans un maison préfabriquée É U seulement ou mobile déjà installée à demeure si les réglements locaux le permettent Manufactured Home installations must be installed in ...

Page 6: ... Degree Elbow Secure Vent Secure Flex flex elbow 52 1321 53 3 4 1365 Includes 4 clearance to combustibles required above vent components MINIMUM CLEARANCES Inches millimeters Back 1 2 in 13 mm Sides 1 2 in 13 mm Top Spacers 0 in 0 mm Floor 0 in 0 mm FromBottomofUnit To Ceiling 64 in 1626 mm Vent 3 76 Top 1 25 4 Sides Bottom SERVICE CLEARANCES Feet meters Front 3 feet 0 9 meters Table 6 Do not insu...

Page 7: ... 91 cm 3 feet 91 cm J Clearance to non mechanical air supply inlet to building or the combustion air inlet to any other appliance 6 in 15 2 cm for appliances 10 000 BTU hr 3kW 12 in 30 cm for appliances 10 000 BTU hr 3kW and 100 000 BTU hr 30kW 36 inches 91 cm for appliances 100 000 BTU hr 30kW 6 in 15 2 cm for appliances 10 000 BTU hr 3kW 9 in 23 cm for appliances 10 000 BTU hr 3kW and 50 000BTU ...

Page 8: ... according to local codes these instructions the current National Fuel Gas Code ANSI Z223 1 in the USA or the current standards of CAN CGA B149 1 and B149 2 in Canada Horizontal Vent Termination Clearances The horizontal vent termination must have a minimum of 3 76 mm clearance to any overhead combustible projection of 2 1 2 64 mm or less See Figure 7 For projections exceeding 2 1 2 64 mm see Figu...

Page 9: ...ed in Figure 9 unless the appliance is to be installed in a corner See Figure 10 for corner framing installations All framing details must allow for a minimum clearance to combustible framing members as shown in Table 6 on Page 6 If the appliance is to be elevated above floor level a solid continuous platform must be constructed Headers may be in direct contact with the appliance top spacers but m...

Page 10: ...2 191 Outer 36 23 32 933 21 1 16 535 1 7 8 48 6 1 16 154 8 7 32 209 1 1 2 38 15 1 32 382 15 15 32 393 7 11 16 195 34 864 40 1 32 1017 20 3 4 527 14 3 4 375 5 13 32 137 Due to Lennox ongoing commitment to quality all specifications ratings and dimensions are subject to change without notice Figure 11A FIREPLACE specifications ...

Page 11: ...ice With the facade installed required sold separately the appliance base will need to be elevated a minimum of 3 4 above the floor to allow for the proper fit of the facade i e use 3 4 board minimum as platform Figure 11B FACADE specifications Facade Required arched style shown 26 3 4 680 38 1 2 978 20 1 4 514 14 13 16 376 1 2 13 1 2 13mm 1 1 2 38mm Arch Facades Black and Brushed Nickel Finishes ...

Page 12: ...cation The following sections describe vertical roof and horizontal exterior wall vent applications Refer to the section relating to your installation A list of approved venting components are shown in the tables on Page 30 Vertical Termination Systems Roof Figures 17 and 23 through 25 on Pages 14 and 16 and their associated Vertical VentTablesillustratethevariousverticalventing configurations tha...

Page 13: ...1 2 0 0 3 7 5 5 7 4 0 0 1 1 0 2 6 6 5 2 5 0 2 2 0 0 4 5 7 6 5 2 6 5 0 0 3 0 0 3 9 6 5 7 5 0 0 0 2 0 2 2 7 6 1 0 3 0 0 4 5 3 7 5 2 1 6 1 0 0 2 0 3 5 9 7 5 2 6 6 0 1 0 2 0 3 1 8 5 7 6 0 0 0 1 1 2 0 9 5 7 0 2 1 0 1 4 5 1 9 5 2 6 7 0 0 2 0 1 3 3 9 5 7 7 0 0 0 0 2 2 6 9 8 1 0 1 2 0 4 5 7 9 5 2 1 8 1 0 0 0 2 3 2 0 1 5 8 2 0 0 0 2 4 5 3 0 1 5 2 6 8 0 0 0 3 0 3 8 0 1 9 1 0 0 3 0 4 4 1 1 5 9 0 2 0 0 2 4 7 ...

Page 14: ...gthedimplesdown and along the incline channels until they seat at the end of the channels This seating position is indicated by the alignment of the arrow and dimple as shown in Figure 16 D Install firestop spacer at ceiling When usingSecureVent useSV4 5VFfirestop spacer at ceiling joists when using Secure Flex use SF4 5VF firestop spacer If there is living space above the ceiling level the firest...

Page 15: ...Page 7 The SV4 5CGV 1 Vertical Termination Figure 22 installs in the exact same fashion as any other Secure Vent section Align the termination over the end of the previously installed section adjusting the radial alignment until the four locking dimples of the termination are aligned with the inlets of thefourinclinechannelsofthelastventsection Pushtheterminationdownuntilitfullyengages thentwistth...

Page 16: ...acer SF4 5VF uCeiling Firestop Spacer SV4 5VF uCeiling Firestop Spacer SV4 5VF vWall Firestop Spacer SV4 5HF uWhen using Secure Flex use Firestop Spacer SF4 5VF vWhen using Secure Flex use Firestop Spacer SF4 5HF WARNING UnderNoCircumstances MaySepa rate Sections of Concentric Flexible Vent Pipe Be Joined Together V H1 H V1 uCeiling Firestop Spacer SV4 5VF vWall Firestop Spacer SV4 5HF Example If ...

Page 17: ...on lengths are available Plan the vent lengths so that a joint does not occur at the intersection of ceiling or roof joists Make allowances for elbows as indicated in Figure 18 on Page 14 Maintain a minimum 1 25 mm clearance to combustibles on the vertical sections Clear ances for the horizontal runs are 3 76 mm on top 1 25 mm on sides and 1 25 mm at the bottom B Frame exterior wall opening Locate...

Page 18: ...m at all sides for all vertical runs and 3 76 mm at the top 1 25 mm at sides and 1 25 mm at the bottom for all horizontal inclined runs J Assemble vent run to exterior wall If not previously measured locate the center of the vent at the exterior wall Prepare an opening as describedinStepB Assembletheventsystem to point where the terminus of the last section is within 6 in 152 mm to 9 1 4 in 235 mm...

Page 19: ... show a 1 V to 5 H ratio up to a maximum horizontal run of 20 feet except for installations where an elbow is the only vertical vent section in the system see Figure 29 AN ELBOW IS ACCEPTABLE AS 1 FOOT OF VERTICAL RISE EXCEPT WHERE AN ELBOW IS THE ONLY VERTICAL COMPONENT IN THE SYSTEM See Figure 29 See Table 7 as an aid in venting component selection for a particular range of exterior wall thickne...

Page 20: ...al run of 20 feet An elbow is acceptable as 1 foot of vertical rise except where an elbow is the only vertical component in the system See Figure 29 V H H1 V1 Wall Firestop Spacer SV4 5HF Ceiling Firestop Spacer SV4 5VF When using Secure Flex use Firestop Spacer SF4 5VF When using Secure Flex use Firestop Spacer SF4 5HF Wall Firestop Spacer SV4 5HF Example If 20 feet total H H1 horizontal vent run...

Page 21: ...vent pipe push it back out of the way 2 ApplyabeadofMill PacBlack 700 F high temperature sealant Catalog No 10K81 to the inner adapter collar approximately 1 2 inch from the end 3 Pull and extend the inner flexible vent pipe 4 Slidetheinnerflexpipeovertheadaptercol lar Ensure the flexible vent pipe completely engages the adapter collar to a distance of 1 3 4 inches from the end and that it is free...

Page 22: ...ure 11A on Page 10 3 Remove the cover plate s knockout and then feedthepowersupplywirethroughtheknock out opening and into the unit junction box 4 Connect the black power supply wire to the red pigtail lead and the white power supply wire to the common terminal of the outlet as shown in Figures 36 and 37 5 Connect the ground supply wire to the pig tail lead attached to outlet s green ground screw ...

Page 23: ...by striking or slamming it Handle this glass with extreme care Glass is susceptible to damage Do not scratch or handle roughly while reinstalling the glass door frame BLOWER CONTROL CIRCUIT WIRING 120V 60HZ 1PH Factory Wired Ground Field Wired Junction Box Tab Intact Tab Broken Plug blower into this receptacle n e e r G d n u o r G Wall mounted ON OFF Blower Switch or Variable Speed Control Switch...

Page 24: ...k for leaks Turn on gas supply and test for gas leaks using a gas leak test solution also referred to as bubble leaksolution Note Usingasoapywatersolution 50 dish soap 50 water is an effective leak test solution but it is not recommended because the soap residue that is left on the pipes fittings can result in corrosion over time Gas Valve 3 8 NPT x Flare Fitting 3 8 Flex Tubing 3 8 Nipple 3 8 Uni...

Page 25: ...enter to provide a natural fire look WARNING DO NOT attempt to install the logs until the appliance installation has been completed the gas line connected and tested for leaks and the initial burner operation has been checked out Logs get very hot and will remain hot up to one hour after gas supply is turned off Handle only when logs are cool Turn off all electricity to the appliance before you in...

Page 26: ...ion the hole on the bottom of log D over pin 3 4 Place the right front log E as shown in Figure 45 Position the hole on the bottom of log E over pins 4 and 5 6 Ember Placement Separate the Embers rockwool into pieces about the size of a quarter see Figure 41 Keep the pieces fluffed up not matted Distribute these pieces over the surface of the burner as shown in Figure 47 Do not use more than is ne...

Page 27: ... Nozzels Figure 49 Figure 48 MILLIVOLT Thermocouple Hood Igniter Rod 3 8 Min 9 mm Thermopile Pilot Nozzels Step 10 Checking Appliance Opera tion With gas line installed run initial system check outbeforeclosingupthefrontoftheunit Follow the pilot lighting instructions provided in the Care and Operation Manual For piezo igniter location see Figure 39 on Page 24 millivolt appliances only Note Lighti...

Page 28: ... switch in the OFF position Close the lower control compartment panel Note See Figure 50 for proper burner flame appearance Air Shutter Adjustment Guidelines If there is smoke or soot present first check the log set positioning to ensure that the flames are not impinging on any of the logs If the log set is properly positioned and a sooting condition still exists then the air shutter opening shoul...

Page 29: ...ion Ahearthextensionisnotrequiredwiththisappliance Ifahearthextension is used do not block the lower control compartment panel Any hearth extension used is for appearance only and does not have to conform to standard hearth extension installation requirements Note Combustible wall finish materials and or surround materials must not be allowed to encroach the area defined by the appliance front fac...

Page 30: ...nt Sections ListedSecureVentComponents Cat No Model Description These termination kits include firestop spacer gear clamps and flex adapter H1969 SF4 5HT 2 HorizontalSquareTermina tion withoutflex 77L87 SFKIT12S FlexSquareTerm with 12inch 305mm compressedflex 77L88 SFKIT18S FlexSquareTerm with 18inch 457mm compressedflex 77L89 SFKIT24S FlexSquareTerm with 24inch 610mm compressedflex 77L90 SFKIT36S...

Page 31: ...nsdufabricantettoutesexigences et codes applicables de l autorisés avoir la juridiction Si l information danscetteinstructionn estpassuivie exactement unfeu explosionoupro ductiondeprotoxydedecarbonepeut résulterledommagescauserdepro priété perteoublessurepersonnelle devie L agencequalifiéedeservice estesponsabledel installationpropre de cet équipment L installation n est pas propre et compléte ju...

Page 32: ...e orifice B Retrieve the burner and slide the venturi tube over the orifice see Figure 53 Set the burner assembly into its position and secure it Figure 56 Burner Orifice Step8 Reassembletheremainingcomponents by reversing the procedures outlined in the preceding steps Use pipe joint compound or Teflon tape on all pipe fittings before installing ensurepropaneresistantcompoundsareused in propane ap...

Reviews: