Group 5
Transport/Start up
Page 49
JET3up
Release R1.06
5.4
Start-up Commissioning
For a safe transport some hydraulic components are supplied with transportation
protection (cable ties) and the reservoir tanks are evacuated. The following steps
have to be carried out before the initial operation
Remove the transportation protection (cable ties) (Step 1)
Fill the reservoir tank (Step 2)
Carry out the function <Filling Routine> (Step 3)
5.4.1
Remove transportation safety devices - Step 1
The pumps and valves of the hydraulic system are secured with cable ties. These
have
to be
absolutely removed.
Proceeding:
Dismantle the backplane of the hydraulic cabinet
(1)
by loosing the fixing screws
(2)
.
ATTENTION
The cable tie at the main filter (3) should not be removed!
Remove the transportation protection (cable ties).
Now attach the backplane of the hydraulic cabinet again with the according fixing
screws.
Summary of Contents for JET3 up
Page 1: ...Operating Manual V1 06 Please keep for future reference ...
Page 2: ......
Page 18: ...Page 16 Introduction Group 1 Release R1 06 JET3up ...
Page 31: ...Group 2 Safety Page 29 JET3up Release R1 06 ...
Page 37: ...Group 3 Accident prevention Page 35 JET3up Release R1 06 ...
Page 42: ...Page 40 Accident prevention Group 4 Release R1 06 JET3up ...
Page 396: ...Page 394 Appendix List of illustrations Group 12 Release R1 06 JET3up 12 4 2 Print head SK 6 ...
Page 398: ...Page 396 Appendix List of illustrations Group 12 Release R1 06 JET3up 12 4 4 Cabinet LJ ...