z
Open the packing box; remove the packing
materials and inspect the lift for any sign of
shipment damage. Check packing list to see if the
main parts and accessories are complete.
z
Keep the packing materials away from the children
to avoid danger; if the packing materials cause the
pollution, they shall be treated properly.
5. Installation
5.1
Important notice
z
The wrong installation will cause the lift damage or
personal injury. The manufacturer will not
undertake any responsibilities for any damage
caused due to incorrect installation and usage of
this equipment, whether directly or indirectly.
z
The correct installation location shall be
“horizontal” floor to ensure the horizontal lifting.
The slightly slope floor can be corrected by proper
shimming. Any big slope will affect the height of the
lifting pad when at the bottom or the horizontal
lifting. If the floor is of questionable slope, consider
a visual inspection, or pour a new horizontal
concrete slab if possible. In short, under the
optimum horizontal lifting status, the level of the
lifting relies on the level of the floor where it is
installed. Don’t expect to compensate for the
serious slope.
z
Don’t install this lift on any asphalt surface or any
surface other than concrete. The lift must be
installed on concrete conforming to the minimum
requirement showed in the manual. Don’t install
this lift on the concrete with seams or crack and
defect. Please check together with the architect.
z
Without the written approval of the architect, don’t
install this lift on a second floor with basement.
z
Overhead obstruction: The lift installation area
can’t have any overhead obstruction, such as
heater, building support, electrical pipe, etc.
z
Concrete drilling test: The installation personnel
can test the concrete thickness at each site by
drilling test. If several lifts are installed at one place,
it is preferred to make drilling test in each site
z
Power supply: Get ready the power supply before
the installation. All the electric wiring and
connecting should be performed by a certified
electrician.
5.2 Installation procedure
5.2.1 Selecting installation site
Select installation site based on the following conditions:
z
Lift can only be installed on concrete slab, which
must have a minimum thickness of 250mm and
should be aged 7days at least .
z
The concrete slab shall have reinforcement by steel
bar.
z
The concrete slab must be leveled.
z
If the thickness of the whole ground concrete is
greater than 250mm, the lift can be installed directly
z
Check the possible obstruction, e.g. low ceiling, top
pipeline, working area, passage, exit, etc.
z
The front and back of the lift should be reserved
with sufficient space to accommodate all the
vehicles(Fig.4).
Fig 4
≤
4.1m TLT245AT
≤
5.1m TLT250AT(C)
Entrance
Summary of Contents for TLT245AT
Page 19: ......
Page 37: ...Launch TLT245AT TLT250AT C Two post lift s Installation manual 16...
Page 38: ...Launch TLT245AT TLT250AT C Two post lift s Installation manual 17 225 2 24 226 227 228 229 229...
Page 44: ...Launch TLT245AT TLT250AT C Two post lift s Installation manual 23...
Page 54: ......