ASSEMBLY

PT Series Hydraulic Circuit 
Installation

WARNING

Tightening Procedure For JIC 37° Swivel Female 

Nuts

1. Check flare and seat for defects.
2. Lubricate the connection.
3. Install hoses without twists.
4. Hand tighten until connection bottoms.
5. Using 2 wrenches to prevent twisting, rotate the swivel 
nut 2 wrench flats (1/3 turn).
6. For reassembly, follow the same procedure but tighten 
only 1 wrench flat (1/6 turn).

Tightening Procedure For Swivel O-Ring Fittings

1. Lubricate O-Ring and install the fitting until the metal
washer which backs up the o-ring contacts the face of the 
boss.
2. Orient the fitting by turning counterclockwise up to 1
turn.
3. Tighten the lock nut using 50-60 foot pounds torque.

Attach the Manual Storage Canister using two 4-1/2 
Hose Clamps.

(See “Hydraulic Fitting Torque Specifications” on 
page 4-2.)

CAUTION

PT Series

You can find the components needed to assemble the 
Hydraulic Circuit in either the Bridge Hitch Box Assembly 
or the Pulverizer General Box Assembly.

Remove Fitting Caps prior to installing Fittings.

Screw a 90 degree Male ORB X Male JIC into the rod 
end port and a 90 degree Male ORB x Female Swivel JIC 
Elbow Fitting into the base end port of the Hydraulic 
Cylinder. Screw a Restrictor into the Ball Valve port that 
will connect up to the base end of the hydraulic cylinder 
and a Male ORB X Male JIC Adapter Fitting into the other 
port of the Ball Valve. Connect the Ball Valve Restrictor 
to the Elbow in the base end port of the Cylinder. 
Assemble Bulkhead Fittings into the bulkhead plate 
located on the top of the of the Bridge Hitch Tube. 

Connect 3/8 x 185 Hose Assembly to the Cylinder rod 
end Elbow Fitting and 3/8 x 161 Hose Assembly to the 
Ball Valve Adapter Fitting. Route hose up the Bridge 
Hitch connecting them to the Bulkhead Fittings. Connect 
3/8 x 150 Hose Assemblies to the bulkhead fittings and 
route them along the Bridge Hitch to the Gooseneck 
Coupler. Turn a 90 degree Male JIC x Female Swivel JIC 
Elbow Fittings into the end of the Hoses. Assemble Male 
ORB X Male JIC Adapter Fittings into Male Couplers and 
turn them into Elbow Fittings at the end of the Hoses.

Secure hoses with Twin Clamps, Top Plate and 5/16-18 
1-1/4 Bolts in the mounts provided on the Bridge Hitch. 

See Figure 2-9.

Ag Harness Installation

Connect Ag Harness to the Pulverizer Light Module. 
Route the Ag Harness with the Hydraulic Hoses along 
the Bridge Hitch to the Gooseneck Couple. Bundle and 
Secure Harness to the Hoses with Tie Straps.

Escaping fluid under pressure can be nearly 
invisible and have enough force to penetrate the 
skin causing serious injury. Use a piece of 
cardboard, rather than hands, to search for 
suspected leaks. Wear protective gloves & safety 
glasses or goggles when working with hydraulic 
systems.

Do not raise the machine without the use of 
hydraulics. This would introduce air into the 
hydraulic cylinder. When the transport pin is 
removed the frame would lower rapidly possibly 
causing injury.

Summary of Contents for Brillion BH1020

Page 1: ...F 778 R0 LANDOLL CORPORATION 1900 North Street Marysville Kansas 66508 785 562 5381 800 428 5655 WWW LANDOLL COM s Bridge Hitch Model BH1020 Operator s Manual...

Page 2: ......

Page 3: ...k Coupler Installation 2 2 Bridge Hitch Installation 2 3 PFT Series Brace Installation 2 4 PT Series Brace Installation 2 5 PFT Series Hydraulic Circuit Installation 2 8 PT Series Hydraulic Circuit In...

Page 4: ......

Page 5: ...ts may have changed to assure top performance Location reference Right and Left designations in this manual are determined by facing the direction the implement will travel during field operation unle...

Page 6: ...ls through your Brillion dealer Keep these signs clean so they can be observed readily It is important to keep these decals cleaned more frequently than the implement Wash with soap and water or a cle...

Page 7: ...implement so it will not roll when working on or under it to prevent injury Do not make adjustments or lubricate the machine while it is in motion Make sure all moving parts have stopped Understand th...

Page 8: ...ications If two or more implements are pulled in tandem a larger chain may be required Chain capacity must be greater than the TOTAL weight of all towed implements A second chain should be used betwee...

Page 9: ...not use fingers or skin to check for leaks Lower load or relieve hydraulic pressure before loosening fittings 3K706 528934 4K039 CAUTION MOVING MACHINES CAN CAUSE INJURY KEEP AWAY 1 KEEP AWAY FROM MO...

Page 10: ...1 6 F 778 INTRODUCTION AND SAFETY INFORMATION Figure 1 4 Decal Locations BH1020 Decals 8J309 528934 4K309 528934 3K706 8J309 3K706 3K706 8J309 528934 4K309 528934...

Page 11: ...embled parts or fasteners are temporarily removed remember where they go It is best to keep the parts separated Check that all working parts move freely bolts are tight and cotter pins are spread Refe...

Page 12: ...Hitch by sliding three 1 inch Washers into the slotted end of the chain place two 1 inch Washers between the chain and the Bridge Hitch Insert 1 8 x 9 1 2 Bolt through the chain washers and hitch sec...

Page 13: ...ge Hitch See Figure 2 2 Figure 2 2 PFT Series Installation PT Series Bring the rear of the Bridge Hitch into position between the frame hitch plates at the center of the frame Place one 1 1 4 x 1 7 8...

Page 14: ...hole below Insert 5 8 11 x 8 1 2 Bolts through the holes and secure with Locknuts These locknuts should be tightened securely 110 ft lb Rotate the Left and Right hand Hitch Braces so they are against...

Page 15: ...Insert 1 2 13 x 8 Bolts through the holes and secure with Locknuts These locknuts should be tightened securely 110 ft lb Rotate the Left and Right hand Hitch Braces so they are against the Upper Bridg...

Page 16: ...nder rod or raise the frame slightly to make this connection Use the cylinder pins packaged with the cylinder to attach the cylinder to the machine Be sure to bend the cotter pins so that the cylinder...

Page 17: ...alled Extension Lug and the rod end of the Hydraulic Cylinder to the Pulverizer lug It may be necessary to extend the cylinder rod or raise the frame slightly to make this connection Use the cylinder...

Page 18: ...the Cylinder Turn a 90 degree Male JIC x Female Swivel JIC Elbow Fitting onto the Restrictor in the rod end port of the Cylinder Assemble Bulkhead Fittings into the bulkhead plate located on the top o...

Page 19: ...RB Restrictor 08M JIC x 08M ORB Bolt 5 16 18 x 1 1 4 Twin Clamp Pair Top Plate Male Coupler Adapter 08M JIC x 08M ORB 08F JIC x 08F JIC x 90 Deg Elbow Restrictor 08M JIC x 08M ORB 08M ORB x 08F JIC x...

Page 20: ...ther port of the Ball Valve Connect the Ball Valve Restrictor to the Elbow in the base end port of the Cylinder Assemble Bulkhead Fittings into the bulkhead plate located on the top of the of the Brid...

Page 21: ...08M ORB 08F JIC x 08F JIC x 90 Deg Elbow Bulkhead Adapter Bolt 5 16 18 x 1 1 4 Twin Clamp Pair Top Plate Ball Valve Adapter 08M JIC x 08M ORB Restrictor 08M JIC x 08M ORB 08M ORB x 08F JIC x 90 Deg El...

Page 22: ...2 12 F 778 ASSEMBLY Table provided for general use NOTES...

Page 23: ...rod Secure in place by inserting Bent Pin and Hair Pin See Figure 3 1 Field Operation Once the machine has been transported to the field remove the Transport Lock from the cylinder rod Place the Tran...

Page 24: ...Parking Pulverizer with BH1020 Bridge Hitch NOTE Be sure ground is level To prepare for unhitching the towing implement needs to be in Transport position with transport locks installed Lower Parking S...

Page 25: ...50 65 81 90 112 9 16 12 55 62 80 100 110 137 9 16 18 60 75 90 112 130 162 5 8 11 75 94 110 137 170 212 5 8 18 85 106 130 162 180 225 3 4 10 130 162 200 250 280 350 3 4 16 150 188 220 275 320 400 7 8 9...

Page 26: ...nufacturer to manufacturer Thick nuts must be used on grade 8 capscrews Use value in if using prevailing torque nuts Dash Size 37 Deg JIC O ring ORS O ring boss 4 11 13 15 17 13 15 5 14 16 21 23 6 20...

Page 27: ...ydraulic circuit is opened air must be bled from the system Check the hydraulic lines and cylinders for leaks before starting operation each day When the machine is not to be used for some time expose...

Page 28: ...4 4 F 778 MAINTENANCE Table provided for general use NOTES...

Page 29: ...5 1 Chapter 5 General Reference and Specifications Table 5 1 Specifications Standard Machine Specifications Parking Stands Safety Chain Powder Coat Paint Red Approximate Set up Time 3 Hours...

Page 30: ...5 2 F 778 GENERAL REFERENCE AND SPECIFICATIONS Table provided for general use NOTES...

Page 31: ...Document Control Revision Log Date Revision Improvement s Description and Comments Team Member 01 2015 R0 Initial Release WML...

Page 32: ...facilities Bridge Hitch Model BH1020 Operator s Manual Re Order Part Number F 778R0 LANDOLL CORPORATION 1900 North Street Marysville Kansas 66508 785 562 5381 800 428 5655 WWW LANDOLL COM F 778 R0 Co...

Reviews: