Section 1: Assembly & Set-up
4/03/14
PS25120 Primary Seeder 313-156M
Three-Point Primary Seeder
Your 3-Point 25 Series Primary Seeder is shipped to you
almost completely assembled. Carefully follow
instructions below for final assembly.
Check all nuts to make sure they are tight. See "Torque
Values Chart for Common Bolt Sizes" on page 35 for
torque specifications.
Parking Stand Assembly
1.
Remove seeder from its crating.
Refer to Figure 1-2:
2.
Install parking stand bracket (#1) on the left end of
the seeder frame with two 5/8"-11 x 2 1/4" GR5 cap
screws (#2), one flat washer (#3), two lock
washers (#4), and two hex nuts (#5). Be sure to use
flat washer (#2) in the location shown to ensure
proper installation of bracket.
3.
Tighten hex nuts to the correct torque.
4.
Insert parking stand (#6) into bracket (#1) until the
top hole is above the bracket tube. Install wire
retaining pin (#7) in the top hole and secure in place
with wire retainer.
5.
Install wire retaining pin (#8) in one of the three holes
below when using the stand for parking. Raise
parking stand fully up and install wire retaining
pin (#8) in the very bottom hole when storing the
stand for transporting and field use.
Acremeter Installation
Refer to Figure 1-3:
Screw acremeter (#1) fully onto the right-hand drive
shaft. Hand tighten.
Parking Stand Installation
Figure 1-2
Acremeter Installation
Figure 1-3
15225