  Purge the carbonator of air by lifting the relief valve until water discharges from the CO2 

exhaust port.  For dual carbonators, repeat this operation for each carbonator. 

 

 

Caution 

Maximum water supply pressure to be 275 kpa. 

Normal operating water temperature should be within 7°C to 32°C.

 

 

3.7  Connecting to CO2 supply 

 

Warning 

As carbon dioxide (CO

2

) displaces oxygen; prevention of CO

2

 leaks is 

paramount. If a leak is suspected, immediately ventilate the 

contaminated area, before attempting repairs. 

 

  Connect CO2 supply line from regulator to gas inlet on carbonator. (See Postmix circuit 

diagram page 11 – 13 for details) 

  Adjust CO2 Regulator supplying Carbonator to 550 kpa. 

  Turn on CO2 supply. 

 

3.8  Filling unit with water 

Remove Superchiller lid and fill water bath until water flows out overflow tube. 
NOTE: Do not use water supplied from newly installed carbon filter as ice bank control 

operation will be adversely affected. 

 

3.9  Electrical Connection 

  This unit requires a separate 10 amp (Postmix) and a 15amp (Refrigeration) power 

supplies. 

  Check the name plate on the machine for electrical supply requirements. Use only the 

power supply specified on the name plate. 

 

 

Warning  If the supply cord is damaged, it must be replaced by the manufacturer, 

its service agent or similarly qualified persons in order to avoid a hazard. 

 

 

Warning 

To avoid possible fatal electric shock or serious injury the Superchiller 

must be electrically grounded.  

Electrical Connection Must Be Made In Accordance With The 

Appropriate Local Codes And Regulations.  

Use of an RCD is recommended.

 

 

3.10  Plumbing the drain and CO2 exhaust 

The 19mm overflow drain tube exiting from the base of the tank should be plumbed to a 

suitable drain, installation in accordance with AS/NZS 3500.1 and AS/NZS 3500.2.  
The 6mm barb labelled as CO2 EXHAUST should be plumbed to an outside safe area. 

 

3.11  Commissioning 

  Unplug carbonator and recirculation pumps power supply leads from electrical box located 

under lid. 

  Connect Superchiller power supply lead to an appropriate 3 pin socket outlet and switch on. 

Compressors, condenser fans and agitator motors should all operate. 

  When Superchiller ice bank is fully formed (approx. 4 hours) the compressors and 

condenser fans will cycle off, but the agitators will run continuously (unit has cycled off). 

  After Superchiller has cycled off, reconnect carbonator and recirculation pumps. 

Summary of Contents for S8E V3 Series

Page 1: ...www lancerbeverage com S8E V3 Hi Carb Superchiller 230V 50Hz Installation Operation Service Manual...

Page 2: ...erbeverage com Page 2 of 27 Hoshizaki Lancer reserve the right to change specifications without notice Part No 68000021 Images are for illustration purposes only as product may vary No 043 3 19 Decemb...

Page 3: ...with water 8 3 9 Electrical Connection 8 3 10 Plumbing the drain and CO2 exhaust 8 3 11 Commissioning 8 3 12 Purge System 9 3 13 Sanitise System 9 4 Scheduled Maintenance 9 4 1 Daily 9 4 2 Quarterly 9...

Page 4: ...80 litres Construction Stainless Steel Compressor Danfoss x 2 Agitator Motor 12W 230 VAC 1 Phase Condenser Motor 20W 230 VAC 1 Phase Ice bank Control Electronic Carbonation Level Control Electronic Dr...

Page 5: ...n injury or equipment damage 2 3 Operating Warning Superchillers are intended for indoor operation only do not operate outside unless suitably protected by a weatherproof enclosure This appliance is n...

Page 6: ...m with the carrier 3 2 Unpacking Caution The use of gloves is recommended to protect hands from potential injury from sharp edges The Superchiller must always be handled in a vertical position Careful...

Page 7: ...carbonator or 3 pumps single carbonator python should be connected to Chiller as follows 5 Pump 4 Pump 3 Pump SODA RETURN A WATER RETURN SODA RETURN B SODA RETURN A SODA RETURN B SODA RETURN A WATER R...

Page 8: ...requires a separate 10 amp Postmix and a 15amp Refrigeration power supplies Check the name plate on the machine for electrical supply requirements Use only the power supply specified on the name plate...

Page 9: ...nnects and re connect disconnects to appropriate BIB s Operate dispensing valves until syrup flows freely 4 Scheduled Maintenance The following Superchiller routine maintenance should be performed at...

Page 10: ...res per minute replace pump Commission and purge system as per clause 6 11 and 6 12 4 5 Sanitisation of Beverage System To maintain optimum quality of dispensed product each Superchiller and its assoc...

Page 11: ...age 11 of 27 Hoshizaki Lancer reserve the right to change specifications without notice Part No 68000021 Images are for illustration purposes only as product may vary No 043 3 19 December 2019 5 Postm...

Page 12: ...of 27 Hoshizaki Lancer reserve the right to change specifications without notice Part No 68000021 Images are for illustration purposes only as product may vary No 043 3 19 December 2019 5 2 Twin Carb...

Page 13: ...13 of 27 Hoshizaki Lancer reserve the right to change specifications without notice Part No 68000021 Images are for illustration purposes only as product may vary No 043 3 19 December 2019 5 4 Twin Ca...

Page 14: ...om Page 14 of 27 Hoshizaki Lancer reserve the right to change specifications without notice Part No 68000021 Images are for illustration purposes only as product may vary No 043 3 19 December 2019 6 E...

Page 15: ...lancerbeverage com Page 15 of 27 Hoshizaki Lancer reserve the right to change specifications without notice Part No 68000021 Images are for illustration purposes only as product may vary No 043 3 19...

Page 16: ...z www lancerbeverage com Page 16 of 27 Hoshizaki Lancer reserve the right to change specifications without notice Part No 68000021 Images are for illustration purposes only as product may vary No 043...

Page 17: ...if necessary fit burnout drier to industry standards Compressor short cycling on thermal overload frequent starting and stopping of the compressor while ice bank control contacts remain closed Dirty...

Page 18: ...aper cups Dirty or greasy glasses Improperly drawn drink Check carbonator control using procedure on page 21 Replace control or probe if defective Check filters Check CO2 pressure at regulator Should...

Page 19: ...ll not run due to excessive carbonator CO2 pressure Faulty low pressure switch Defective Carbonator motor Locked up pump Motor has cut out on overload Carbonator empty faulty control board or level pr...

Page 20: ...VAC is present on terminals N A ON 1 ON 2 terminals Work should only be performed by fully trained certified Electrical Plumbing Refrigeration Technicians 1 Remove the ice bank probe connections from...

Page 21: ...ning 230VAC is present on terminals N A ON 1 ON 2 Work should only be performed by fully trained certified Electrical Plumbing Refrigeration Technicians 1 Remove the carbonator probe connections from...

Page 22: ...9 BACKFLOW PREV ANDERSON 6 08000002 CARBONATOR RELIEF VALVE 7 63000163 COIL ASSY PRECHILL B 8 87000052 STRAINER FLOW INDICATOR 10 63000164 COIL ASSY SODA A 11 63000165 COIL ASSY SODA B 12 63000205 COI...

Page 23: ...lancerbeverage com Page 23 of 27 Hoshizaki Lancer reserve the right to change specifications without notice Part No 68000021 Images are for illustration purposes only as product may vary No 043 3 19 D...

Page 24: ...8 83000324 ELECTRICAL BOX ASSY 4P 5P S8E V2 83000325 ELECTRICAL BOX ASSY 3P S8E V2 9 83600811 MINI CONTACTOR C15 9 DANFOSS 10 83000278 CONTROL LEVEL I B HYDRA R2 11 83000282 COMPRESSOR START RELAY AN...

Page 25: ...cerbeverage com Page 25 of 27 Hoshizaki Lancer reserve the right to change specifications without notice Part No 68000021 Images are for illustration purposes only as product may vary No 043 3 19 Dece...

Page 26: ...of the Divisional Sales Manager Lancer may choose to reimburse the customer for some or all labour costs associated with a warranty claim Any claim for labour costs must be authorized by Lancer prior...

Page 27: ...nd pumps secured and mounted correctly in correct locations All pumps run quietly and carbonator pump switched ON OFF Check icebank probe position and tightness and correct wiring of harness Carbonato...

Reviews: