LEGACY FG
033-0004
Page S.11
REV. 0/04-23-2007
Supplement–Legacy Fixed Gear
Lancair International Inc., Represented by Neico Aviation Inc., Copyright 2007 Redmond, OR 97756
Again, make sure the alignment tool is level!
7. Mark the location of the plumb bob, at the 3’ (1 meter) forward location.
8. Measure the distance from the toe-in line on the floor to the mark at the end of the plumb bob.
This distance needs to be 5/16” (8 mm). Or, in other words the toe-in needs to be 0.5°.
You may need to rotate the axle mount to get the correct amount of toe in. Do this by loosening the set screw,
adjust as needed, and re-tighten the set screw. Now re-level the alignment tool.
Adjust as needed so the distance from the toe-in line to the plumb bob mark is 5/16” (8 mm) more at the 3’
(1 meter) forward mark than the mark at the end of the gear leg.
Figure S.4.C.3 Top view of the gear legs, the lines on the floor and the alignment tools
9. Re-check the dimensions.
• At 3’ (1 meter) in front of the center of the axle mount, the plumb bob needs to be 5/16” (8 mm) inside the line
on the floor.
10. Tighten all screws holding the gear leg and the alignment tool in place.
11. Re-check both plumb bobs, level the alignment tool and the toe-in angle.
Tip:
If the alignment tool is not level, the toe-in angle will not be correct!
When you are satisfied that the toe-in angle is correct, you are ready to mark the bolt locations on the gear leg.
Figure S.4.C.4 Marking the second location at three feet in front of the gear leg
Alignment tool
Toe-in line
3’ (1 meter) forward
of the middle of the
axle mount.
5/16 (8 mm)
Plumb bob needs to be 5/16” (8 mm)
inside the line on the floor.