31
6
Commissioning
6.2
Installation
The following sections provide information on:
•
What prerequisites have to be met to install the product properly
•
How you have to position the product
•
How you have to secure the product
6.2.1
Prerequisite for Mounting the Device Properly
NOTICE
Mounting the device using a holder
If at all possible, mount the flame scanner to the burner/boiler using a holder optimised by
LAMTEC for use with flame scanners. Characteristics see chapter
Note When Using the Device in Explosion-proof Areas
If you do not do this, ensure that the device is insulated in order to prevent any interference
from equalising currents (via the cable shield).
NOTICE
Mounting location
Ensure that the mounting location is easily accessible. During operation of the combustion
plant, you should be able to see the optical monitoring elements well.
WARNING!
The fiber optic flame detector versions F300K.. IR-.. FO with IR sensors may only be used with
the LAMTEC IR Fiber optic FOR...-IR or FOF...-IR.
Summary of Contents for F300K Series
Page 2: ......
Page 26: ...25 5 User Interface 5 2 Menu tree ...
Page 31: ...30 6 Commissioning Marking information on the device Example F300K F300K UI FB30 Warning e g ...
Page 121: ...120 14 Appendix 14 3 EU Declaration of Conformity ...
Page 122: ...121 14 Appendix ...
Page 125: ...124 14 Appendix ...