57
|
www.lakeshore.com
3.5 Pre-Assembly
Testing
The following tests are to be performed prior to assembling the probe system
configuration to ensure the important subsystems are in proper working condition.
3.5.1 Testing the Turbo
Vacuum Pumping
System
A properly functioning turbo vacuum pump and gauge are critical components for
probe station operation. Therefore, the turbo vacuum pump and gauge should be
checked prior to assembly into the probe station setup. This test should be performed
whether the turbo pumping station was purchased from Lake Shore or separately.
Follow this procedure to verify proper operation of the turbo vacuum pump and
gauge:
1. Complete steps 1 through 2 of section 3.6.5.2 to install the gauge on the turbo
vacuum pump.
2. Complete section 6.3.1.1 to test the turbo vacuum pumping system
3. If a Lake Shore installation and training was purchased, record the pressure
achieved on the site preparation form.
The turbo vacuum pump should be capable of achieving <10
-6
Torr after 10 min of
pumping. Failure to achieve this pressure may be the result of a malfunctioning pump
or gauge. Do not continue with probe station assembly if this pressure is not
achieved; contact Lake Shore or your vacuum pump manufacturer directly for
technical assistance.