Initial Operation
Setting to Work
22
Laird Thermal Systems s.r.o
Operation Manual, 387009851
Date: 08/09/2022
Version: 1.0
Liquid-Air Cooling Unit LA 5000
387009381
Fig. 10:
Electrical connections and terminal behind access plate
1
Electric terminal stripe
2 Earth bolt M5
3
Access plate
4 Cable bushings
8)
Remove the access plate after unscrewing the 2 screws.
2)
Feed the mains cable through one of the cable bushings and make the connection to the terminal. Then
do the same with the wires for the implementation of the safety circuit.
3)
Remount the access plate.
After installation of the mains cable connect the unit to mains by inserting the mains plug or making a mains
connection as required by the particular situation.
6.2.4 Carrying out Setting to Work
After connecting the cooling circuit, filling the coolant container and finishing the electrical connections follow
the steps below for setting the unit to work:
1
3
4
2