Commercial Machine Installation Set-up-Check List 
MODELS: BAR-STAR /DIAMANTE/HOTEL V /  L / S SERIES 

 
Confirm power requirements are correct and located within 4 feet of machine, check the outlet with a 
voltage meter prior to delivering the machine. 
 
Confirm water fittings are correct and located within 6 feet of machine. A mandatory 3/8 inch water 
source line is needed. No more than 40 lbs of water pressure is required. If you measure more, then a 
water pressure regulator is required. EG& H sells them, refer to item C350 when ordering. 

 
IMPORTANT:

  The installation of the metric S/S hose line mated to a non-metric water line will not 

require an adaptor if you are using a 3/8” water line 

 

Confirm that water is flowing out of the building pipe, then install the water softener and confirm flow 
from filter is sufficient.  A water turnoff valve is mandatory.  
 
Confirm that the water softener levers are in the correct position referring to diagram in carton. 
 
Install the adjustable feet located in the parts box and place the unit in location and level the machine via 
the legs. An uneven machine will not drain the excess water properly.  Install the water line then install 
the  power  plug

.  LEVER  MACHINES

:  Insert  the  handles  and  6  inch  chromed  extenders  onto  the 

machine,  the  chrome  extenders  should  be  tightened  with  an  open  end  wrench  (look  at  notch  at  the 
bottom of the extenders) A loose lever can cause the group to misalign. Occasionally check them. 
 
Hook-up  the  water  line  then  install  power  plug.  230V  machines  do  not  have  plugs  attached  as  codes 
differ per County/State. Your electrician should advise you which is the correct plug/outlet combination 
to purchase. Check that the machines wattage and amps match your installed power. 
 

FOR BAR STAR / DIAMANTE MODELS ONLY 
POWER SWITCH LOCATED ON FRONT PANEL:

  0 (12 o’clock position) is the OFF position  

Turn the unit into the next position # 1 (2 o’clock) and allow the boiler to fill past the ½ mark.  This 
should take 10 minutes from a dry start (15 minutes w/1/4” pipe)   Allow the automatic levelers to raise 
the water level, do not use the manual boiler fill. Never allow the boiler to go past ¾ from a cold start as 
water will expand as it warms up. The red light located on the lower left will light up. 
 
Turn  the  unit  to  the  #  3  position  (6  o’clock)  and  allow  the  machine  to  heat-up,  this  will  take 
approximately 25 minutes. This switch position produces maximum power. 
 
When the pressure gauge(s) located under the water tap on the right side of the machine reads 4 on the 
pompa & 1 on the Caldaia (boiler), bleed the unit by opening the steam knobs for 30 seconds each, one 
at a time. 
 
Press  the  hot  water  tap/switch  or  turn  knob,  allow  water  to  flow  into  a  cup  and  check  the  water 
temperature.    Continue  to  allow  water to  flow until  you  hear  the  water  pump  operating  and  view  the 
water level in the sight glass rising. 
 