Rigging procedures
Array removal
About this task
All along the procedure:
Strictly follow the sequence of the successive steps.
Systematically verify that each BLP is fully inserted.
For clarity purposes the loudspeaker cable removal procedure will not be described.
The loudspeaker cables will not be represented on the gures.
Procedure
1.
In case of SB18 standalone array, directly go to step
(p.120).
In case of SB18/Kara mixed array, begin the procedure by applying steps
(p.97) to 13 from the
Array removal
procedure in
Stacking a Kara standalone array using M-BUMP
and then continue to next step.
2.
Unlink the 4 rigging points between the M-BUMP and the SB18 as follows (repeat for each one): remove the TBLP
from the SB18, rotate the arm upwards and lock it by re-inserting the T-BLP on the M-BUMP.
3.
Remove the M-BUMP from the SB18.
For clarity purposes, the procedure is continued with an array composed of two SB18 enclosures.
4.
If not already done, remove the ratchet strap from the array.
5.
Unlink the top SB18 (SB18#2 for example) from the SB18 below (SB18#1 for example) as follows:
a) Disconnect a T-BLP from the top part of SB18#1.
b) Rotate the rigging arm up.
c) Re-connect the T-BLP to SB18#2 so as to lock the rigging arm in closed position.
d) Repeat this procedure until all 4 arms are locked in closed position.
120