Operating Instruction KEA 293 PST -
8 / 12
- File:
BA_KEA 293 PST_EN_Ver 2016-07-01.doc
8
Alfred Kuhse GmbH
Telefon: +49 4171-798-0
E-mail: [email protected]
Subject to technical changes
An der Kleinbahn 39,21423 Winsen
Telefax; +49 4171-798-117
http://www.kuhse.de
13.
Start program
13.1.
Start process, diesel engine
Start delay 2 sec.
Starter on for 10 sec.
Pause 7 sec.
3 start attempts
6 start attempts for sprinkler operation
Delay monitoring on 7 sec.
Sprinkler operation run-on time 0 sec.
Stop time 30 sec.
13.2.
Start process, gas engine
Starter on
If the starter speed is exceeded, the switching-on of the ignition is delayed (e.g. after 2 sec.)
Then (another 2 sec.) open gas solenoid valve
Starter now on for another 7 seconds
Then close gas solenoid valve,
Starter off,
Ignition off after 6 sec.,
New start sequence after 1 sec.
The parameterised standard values for a diesel engine are specified here. If diesel engines with preheating
systems are used, an external preheating button must be provided in the M
ANUAL
selector switch position.
The start delay serves as a preheating time during automatic starts.