RT105M Operator’s Manual
Drill - 109
Operate
Install Product
To install product, pull it through the bore after drilling or final pass of backreaming.
1. Install appropriate swivel (2) to drill string
(1) or reamer. Ensure swivel functions
correctly.
2. Use shackle (3) to attach pipe pulling
adapter (4) or pulling grip (5) to swivel.
3. Attach material to pipe pulling adapter or
pulling grip.
4. Set engine to low throttle.
5. Slowly drive in reverse. See page 75 for
proper driving procedures.
6. When product exits approach trench, stop machine immediately.
Rotating shaft will cause death or serious injury. Stay
away.
To help avoid injury:
Ensure no one is in target trench or near product
being installed. If swivel malfunctions, material can rotate.
IMPORTANT:
•
If bore becomes blocked begin
counterclockwise rotation.
•
If length of rod outside the bore
reaches 30’ (9 m), remove rod
section. See “Remove Rod” on
page 110.
Summary of Contents for RT105M
Page 1: ...RT105M Operator s Manual Issue 2 0 Original Instruction 053 2943...
Page 7: ...Overview 6 RT105M Operator s Manual About This Manual...
Page 25: ...Safety 24 RT105M Operator s Manual Attachment Safety Alerts...
Page 61: ...Controls 60 RT105M Operator s Manual Battery Disconnect...
Page 65: ...Operation Overview 64 RT105M Operator s Manual Leaving Jobsite...
Page 73: ...Prepare 72 RT105M Operator s Manual Check Supplies and Prepare Equipment...
Page 79: ...Drive 78 RT105M Operator s Manual Shut Down...
Page 87: ...Transport 86 RT105M Operator s Manual Retrieve...
Page 95: ...Backhoe 94 RT105M Operator s Manual Finish Job...
Page 96: ...RT105M Operator s Manual Trench 95 Trench Chapter Contents Set Up 96 Operate 98 Finish Job 100...
Page 165: ...Service 164 RT105M Operator s Manual As Needed...
Page 180: ......
Page 181: ......
Page 182: ...RT105M Operator s Manual Service Record 223 Service Record Service Performed Date Hours...
Page 183: ...Service Record 224 RT105M Operator s Manual Service Performed Date Hours...