6 Commissioning/Start-up/Shutdown
26 of 48
Hya-Duo D FL Compact
6 Commissioning/Start-up/Shutdown
6.1 Commissioning/Start-up
6.1.1 Prerequisites for commissioning/start-up
CAUTION
Pump set running dry
Damage to the pump set / break tank package booster set for fire fighting!
▷
Use a dry running protection device. If the dry running protection terminal is
disabled by means of a bridge, the operator shall assume responsibility for any
dry running that might occur.
Ensure that the following requirements are met prior to commissioning/start-up:
▪
The break tank package booster set for fire fighting has been properly connected
to the electric power supply and is equipped with all protection devices.
▪
All relevant VDE standards and/or regulations applicable in the country of use are
complied with.
▪
The owner or the owner's representative must had the system's readiness for
operation and connection conditions checked by the responsible authorities (e.g.
local water provider or the office for industrial safety and product safety).
▪
The dry running protection device has been installed. (