3 Transport/Temporary Storage/Disposal
21 of 116
CHTRa
WARNING
In the case of storage periods of more than 5 years, the sealing function of O-rings
may be impaired.
Rick of injury from leakage of hot, pressurised fluid handled!
▷
After a storage period of more than 5 years, the pump must be dismantled
before it is installed, and the O-rings must be replaced.
▷
Check the O-rings for damage before they are fitted.
3.5 Return to supplier
1. Drain the pump as per operating instructions.
2. Flush and clean the pump, particularly if it has been used for handling noxious,
explosive, hot or other hazardous fluids.
3. If the pump has handled fluids whose residues could lead to corrosion damage
in the presence of atmospheric humidity or could ignite upon contact with
oxygen also neutralise the pump and blow through with anhydrous inert gas to
ensure drying.
4. Always complete and enclose a certificate of decontamination when returning
the pump.
Indicate any safety measures and decontamination measures taken.
(
NOTE
If required, a blank certificate of decontamination can be downloaded from the
following web site:
www.ksb.com/certificate_of_decontamination
3.6 Disposal
WARNING
Fluids handled, consumables and supplies which are hot and/or pose a health
hazard
Hazard to persons and the environment!
▷
Collect and properly dispose of flushing fluid and any fluid residues.
▷
Wear safety clothing and a protective mask if required.
▷
Observe all legal regulations on the disposal of fluids posing a health hazard.
1. Dismantle the pump (set).
Collect greases and other lubricants during dismantling.
2. Separate and sort the pump materials, e.g. by:
- Metals
- Plastics
- Electronic waste
- Greases and other lubricants
3. Dispose of materials in accordance with local regulations or in another
controlled manner.