7.4 

Recommendations for installation 

Before assembly 

Verify that pipeline flanges are free from metallic chips and 
weld splatter. 

Verify that pipeline flanges are located on the same centreline 
and are parallel. 

Verify that inside diameter of pipeline flange is in accordance with 
the minimum and maximum diameters given by the manufacturer. 

Verify that nothing hinders the complete moving of the disc during 
opening  or  closing,  in  particular  at  the  internal  weld  seams  or  at 
the pipe ends. 

Pull apart the pipeline flanges to allow valve insertion without 
damaging the elastomer liner of the valve. 

 

During assembly 

Place the disc as spaced apart as possible from the closing 
position, but without that disc protrudes past the v

alve’s 

body. 

Spread the two pipe flanges to obtain sufficient clearance 
between flange face and valve seat cheeks. 

7.5 

Actuated valves 

 

Electrical cables may only be connected by qualified 

personnel. 

 

The applicable electrical regulations (e.g. IEC and national 

standards),  also  for  equipment  in  hazardous  locations,  must  be 
observed.All  electrical  equipment  such  as  actuator,  switchboard, 
magnetic  valve  drive,  limit  switch  etc.  must  be  installed  in 
floodproof  dry  locations.Voltage  and  frequency  must  match  the 
valves stated on the identity plate. 

 

 

Commissioning/Decommissioning 

8.1 

Commissioning 

8.1.1 

General 

Prior  to  commissioning  the  valve,  the  pressure,  temperature  and 
material data stated on the valve should be compared to the actual 
operating  conditions  in  the  piping  system  to  check  whether  the 
valve can withstand the loads occurring in the system. 

 

 
 
 
 
 
 
 

Minimum clearance : E + 40mm 

E : Face to face valve 

(refer to the type series booklet) 

Insert valve between pipeflanges and center using several tie

rods. 

Screw up progressively the nuts until metal to metal contact is 
achieved between the valve body and pipeline flanges, by making 
sure the good centering of the body compared with the flange is 
maintained. 

Operate the valve several times to ensure no valve disc 
obstruction. 

Possible  pressure  surges  (water  hammer)  must  not  be 

exceed  the  highest  admissible  pressure.  Adequate  precautions 
should  be  taken.In  new  pipe  systems  and  especially  after  repair 
work,  the  system  should  be  flushed  with  the  valves  fully  open  to 
remove solids, 
e.g. weld beads, which may damage the seats. 

 

8.1.2 

Operation 

The position of the disc is indicated by the pointer of the actuator or 
by handle lever. The valves are closed by turning in the clockwise 
direction (top view) and opened in the counterclockwise direction. 

 

8.1.3 

Functional Check 

The  following  functions  should  be  checked:Before  commissioning, 
the  shut-off-function  of  the  valves  should  be  checked  by  repeated 
opening and closing. 

 

8.1.4 

Actuated valves 

Adjustable end stops and torque limiter are pre

adjusted in factory. 

The customer may have to complete the adjustment on site during 
the commissioning, if necessary. 

 

 

8.2 

Decommissioning 

During  extended  shutdown  periods,  liquids  liable  to  change  their 
condition  due  to  polymerization,  crystallization,  solidification  etc. 
must  be  drained  from  the  piping  system.  If  necessary,  the  piping 
system should be flushed with the valves fully open. 

 

9. 

Maintenance/Repair 

9.1 

Safety Instructions 

DN 

 

200 : no maintenance 

Maintenance  and  repair  work  may  only  be  carried  out  by  skilled 
and qualified personnel. 

For  all  maintenance  and  repair  work,  the  safety  instructions  listed 
below  and  also  the  general  notes  in  section  2  must  be 
observed.Always  use  suitable spare  parts  and  tools,  even  in case 
of emergency, otherwise correct operation of the valves cannot be 
assured. 

 
 
 
 
 
 

E + 40 
mini 

Summary of Contents for BOAX- B

Page 1: ...5 9 15 10 BOAX B Mat P 18 11 21 3 G n ralit s 22 4 S curit 23 5 Transport et stockage interm diaire 24 6 Description des robinets 25 7 Installation 26 8 Mise en service et mise l arr t 28 9 Maintenanc...

Page 2: ...12516 4 EN 1563 ASME B16 42 EN 593 EN 10213 H Module H Module H 13 1 2014 68 19 07 2016 D finition en conformit avec article 13 1 2014 68 UE partir du 19 04 2016 Definition in accordance with article...

Page 3: ...ir du 19 04 2016 Ils ne doivent pas tre marqu s du symbole CE suivi du num ro d identification de l organisme notifi Valves DN 50 comply with the Pressure Equipment Directive 2014 68 EU article 4 3 fr...

Page 4: ...25 KE MAMMOUTH 6 10 16 20 25 DANA S 150 DANA S MTII DANA S TBT ACTELEC ACTAIR DYNACTAIR ACTAIR NG DYNACTAIR NG HQ R380 R480 AMTROBOX AMTROBOX R AMTROBOX F R1077 R1078 R1079 R1158 AMTRONIC SMARTRONIC R...

Page 5: ...5 Michel Delobel 6 06 17...

Page 6: ...MARTRONIC Tous Types R1011 R886 R1007 R834 d clarons que les exigences essentielles appliqu es ci dessous 1 1 3 1 1 5 1 2 1 1 3 2 1 3 4 1 3 7 1 3 8 1 3 8 1 1 4 1 1 4 2 1 1 5 1 1 5 2 1 5 3 1 5 4 1 5 7...

Page 7: ......

Page 8: ...4 declare the following essential requirements of the annex I of the Machine Directive 2006 42 EC are applied and fullfilled 1 1 3 1 1 5 1 2 1 1 3 2 1 3 4 1 3 7 1 3 8 1 3 8 1 1 4 1 1 4 2 1 1 5 1 1 5 2...

Page 9: ...7 3 KSB 5 KSB EN ISO 9001 2014 68 2006 42 EC www ksb com Produkte 4 4 1 ISO 3864 B 3 1 ISO 3864 B 3 6 KSB 5 4...

Page 10: ...8 4 2 4 3 4 4 4 5 IEC 364...

Page 11: ...9 4 6 4 6 1 60 C 4 6 2 BOAX B 2 4 5 1 2 XU XC K DN 200 PS P 12 DN 250 500 PS P 7 1 XU XC K DN 200 PS P 12 DN 200 PS P 7 2 XU XC K DN 200 PS P 12 DN 200 PS P 7 PS P 1013 0 5 4 7 4 8...

Page 12: ...10 1 2 3 4 5 6 7 8 9 PS P DN 32 40 50 65 80 100 125 150 200 10 16 5 5 1 5 2 5 6 DN PS P BOAX B 40 1000 10 16 8409 11 6 1 2014 68 1 2 3 PN 4 5 6 7 8 9 01 07...

Page 13: ...0 1000 310 3 40 1000 310 4 350 600 412 40 600 412 1 650 1000 412 2 650 1000 412 3 650 1000 413 40 1000 486 650 1000 540 650 1000 550 40 1000 561 650 1000 900 1 40 600 900 2 250 600 904 650 1000 916 40...

Page 14: ...12 6 4 100 213 210 550 413 DN 200 DN 200 DN 200 ISO 5211 7 7 1 100 Ra 25 DN 600 DN 600 7 2 7 2 1 60 C 0 C 1 2 3 4 70 1 DN 2 3DN 1 DN DN 5 6 DN DN DN 1 DN 2 3DN 2 3DN 1 DN DN DN DN...

Page 15: ...78 250 250 10 276 5 273 249 243 234 306 300 12 327 5 324 297 291 283 358 350 14 361 356 326 321 314 399 400 16 412 407 370 366 358 452 450 18 463 457 422 416 409 505 500 20 515 508 470 464 457 558 600...

Page 16: ...14 E 40 7 4 6 2 2 E 40 E 7 5 IEC 8 8 1 8 1 1 8 1 2 8 1 3 8 1 4 8 2 9 9 1 DN 200 2 E...

Page 17: ...15 9 2 10 60 C KSB 9 3 9 3 1 DN 200 9 3 2 9 3 3 SF amlub...

Page 18: ...16 9 4 9 4 1 916 176 932 900 559 213 210 550 413 412 9 4 2 413 100 550 DN 250 600 900 1 900 2 210 486 940 932 554 901 213 940 550 900 916 176 559 176 904 920 9 5 N M 10...

Page 19: ...17 10 BOAX B Mat P BOAX B Mat P da ACTAIR NG BOAX B Mat P sa DYNACTAIR NG KSB 30 10 C 18 F 30 C 22 F 4...

Page 20: ...M6 10 11 M14 125 135 M8 20 23 M16 190 200 M10 45 50 M20 370 390 DYNACTAIR NG 25 ACTAIR NG 0 10 2 18 24 28 4 28 28 ACTAIR NG 2 2 54 ACTAIR NG 5 2 18 ACTAIR NG 10 1 55 ACTAIR NG 20 2 ACTAIR NG 30 1 45...

Page 21: ...IR NG 0 10 18 24 4 28 28 DYNACTAIR NG 2 2 26 DYNACTAIR NG 4 2 DYNACTAIR NG 6 2 14 DYNACTAIR NG 8 1 54 DYNACTAIR NG 12 1 40 DYNACTAIR NG 16 1 54 28 2 DYNACTAIR NG 28 22 2 4 24 18 ACTAIR NG DYNACTAIR NG...

Page 22: ...20 11 11 1 11 2 KSB KSB KSB BOAX B Mat P BOAX B Mat P BOAX B Mat P...

Page 23: ...r es par le mot Le non respect de cette r gle est susceptible de causer des dommages et blessures tant au personnel qu aux installations Blessures dues aux fuites de liquide froid chaud inflammable ou...

Page 24: ...e l annulation pure et simple de la garantie Cela pourrait par exemple aboutir la non obtention des fonctions essentielles robinet usine des r sultats non satisfaisants des proc dures d entretien et r...

Page 25: ...onsid r s comme liquides les fluides dont la pression de vapeur la temp rature maximale admissible est inf rieure ou gale 0 5 bar au dessus de la pression atmosph rique normale 1013 mbar Fluide danger...

Page 26: ...00 310 3 Palier lisse 40 1000 310 4 Palier lisse 350 600 412 Joint torique 40 600 412 1 Joint torique 650 to 1000 412 2 Joint torique 650 1000 412 3 Joint torique 650 1000 413 Manchette 40 1000 486 Bi...

Page 27: ...brides doivent tre utilis s pour le bridage Les robinets DN 600 peuvent tre mont s en toutes positions Les robinets DN 600 ont un sens pr f rentiel de montage arbre horizontal suivant figure ci dessou...

Page 28: ...450 18 463 457 422 416 409 505 500 20 515 508 470 464 457 558 600 24 617 610 566 560 554 664 650 26 668 620 614 608 723 700 28 718 671 666 660 773 750 30 770 717 711 705 830 800 32 820 769 764 758 88...

Page 29: ...on fonctionnelle Les fonctions suivantes doivent tre v rifi es Avant la mise en service on v rifiera la fonction fermeture en r p tant plusieurs fois les man uvres de fermeture et d ouverture 8 1 4 Ro...

Page 30: ...in de ne pas se trouver sur la trajectoire de l obturateur 9 3 2 Liste d outillage pour le d montage et le montage Visseuse pneumatique jeu de cl s plates cl s six pans cl s pipe tournevis massette po...

Page 31: ...pneumatique sur le robinet Les ACTAIR NG sont pr vus pour fermer les robinets en sens horaire but e r glable en fermeture Il faut obligatoirement les monter en position N actionneur perpendiculaire la...

Page 32: ...28 Type actionneur Angle de variation apr s ajustement de l arbre DYNACTAIR NG 2 2 26 DYNACTAIR NG 4 2 DYNACTAIR NG 6 2 14 DYNACTAIR NG 8 1 54 DYNACTAIR NG 12 1 40 DYNACTAIR NG 16 1 54 Si le robinet e...

Page 33: ...ec kit obturateur appropri R glage des vis de fond paragraphe 8 4 2 Arbre cass tordu Expertise d faut analyse causes remplacement arbre Manchette us e endommag e Remplacement manchette kit manchette M...

Page 34: ...consideration incidents which may occur during installation and operation the local safety regulations lt is the user s responsibility to ensure that these are also observed by the installation staff...

Page 35: ...nsuring that the contents of these operating instructions are fully understood by the personnel involved 4 3 Danger or nonobservance of the safety instructions Nonobservance of the safety instructions...

Page 36: ...PED NB A valve fitted at the end of a pipe with a blind flange downstream is not to be considered as an end of pipe service 4 7 Unauthorized Modification The equipment shall not be altered or modifie...

Page 37: ...ng 40 to 600 412 1 O Ring 650 to 1000 412 2 O Ring 650 to 1000 412 3 O Ring 650 to 1000 413 Liner 40 to 1000 486 Ball 650 to 1000 540 Split bush 650 to 1000 550 Disc 40 to 1000 561 Grooved nail 650 to...

Page 38: ...ings the pivot bearing is relieved it is a guarantee of long valve life specially in the case of fluids containing solids where sold particles tend to accumultate on the bottom of the pipe during the...

Page 39: ...63 457 422 416 409 505 500 20 515 508 470 464 457 558 600 24 617 610 566 560 554 664 650 26 668 620 614 608 723 700 28 718 671 666 660 773 750 30 770 717 711 705 830 800 32 820 769 764 758 880 900 36...

Page 40: ...ipeflanges and center using several tie rods Screw up progressively the nuts until metal to metal contact is achieved between the valve body and pipeline flanges by making sure the good centering of t...

Page 41: ...erator interferes with the disc travel 9 3 2 List of tools for mounting dismantling Pneumatic screwing machine open ended spanner ring spanner box spanner screwdrivers hammer pneumatic polisher wedges...

Page 42: ...unting onto the valve ACTAIR NG has been designed to close the valve in clockwise direction It is designed to be fitted in N position actuator perpendiculary to the piping Operate the actuator up to o...

Page 43: ...stment screws on the springs cylinder 22 Warning The spring return close adjustment is not a mechanical stop that acts against the pistons travel or the shaft rotation but the screws limit the spring...

Page 44: ...using the disc kit Adjust bottom screws Broken shaft twisted shaft Analyse the defect research of causes replace shaft Worn out liner Replacement liner liner kit Receding liner damaged liner If the li...