16
Settings
16.22 Setting the plunger
240
BiG Pack 1270 XC
Original Operating Instructions 150000748_01_en
16.22
Setting the plunger
BP000-210
The four cam rollers (1) in the baling ram must provide equal support.
16.22.1
Setting plunger blades
In order to ensure that the under side of the big bale has a smooth surface, the baling ram blade
must be set accurately.
BPG000-042
•
The bale channel is equipped with 2 counterblades.
•
The plunger (1) is equipped with 7 blades.
ü
The machine is shut down and safeguarded,
.
Trigger the tying process manually with machine at standstill,
Turn the flywheel manually in working direction until the blades (2) are positioned above the
counterblade (3),
Check the dimension X between blade (2) and counterblade (3).
Æ
If the dimension is
X=2-4 mm
, the setting is correct.
Æ
If the dimension is
not
X=2-4mm
, the plunger must be raised or lowered via the eccentric
rolls.