Seatex Seapath 200 Installation Manual, rev. 13
Installation
10
In addition to the above delivered parts, the following is needed:
•
GPS antenna cables and the cable between the Processing Unit and the MRU junction
box.
•
A 19-inch rack for mounting of the Processing Unit.
•
Gyro compass data on a serial line (recommended).
•
DGPS corrections on one or more serial lines for improved position accuracy
(recommended).
•
Additional cables for input of Gyro compass data and DGPS corrections, and for output
lines to external equipment.
•
Devices for reference measurements of roll, pitch and heading (for calibration).
•
An external IBM-compatible PC with MS-Windows for setup and calibration.
General arrangement drawings of the ship should be acquired to simplify determination of
offsets between the GPS antennas, the MRU and the ship's centre of gravity (CG). Locations
for the various parts of the system must be decided, and mounting arrangement for the
Antenna Bracket and sufficient lengths of cable made available.
For external interfaces, electrical characteristics and data formats must be decided, and the
necessary cables and connectors made available. Power supply for the Processing Unit and an
external computer for setup and calibration are also needed.
An external heading reference, for example a surveyed quay is required for heading
calibration. For some applications, pitch and roll reference for calibration is also needed.
The MRU unit is shipped in a specially designed transportation container. Keep the MRU
within the container until everything is ready for installing the unit in the mounting bracket.
Note
After the installation, please save the transportation container. The MRU must be
shipped in this container for service or repair to maintain the warranty.
3.2
Logistics
Safety:
General safety guidelines to be followed when working in mast and on deck.
Personnel qualifications:
Trained electrical workers.
Minimum number of personnel:
2, especially when mounting the Antenna Bracket to the Holder.
Ship location:
The GPS antennas have to be mounted such that blocking of the GPS signal is
avoided. The MRU 5 unit is preferably mounted low in the ship or close to the system to be
compensated. The Processing Unit can be mounted on the bridge or in the instrument room.
Special tools required:
A PC with Microsoft Windows 95, 98, NT version 4.0 or compatible.
Summary of Contents for Seatex Seapath 200
Page 1: ...Seatex Seapath 200 Installation Manual Issued 2008 06 09 ...
Page 2: ...Blank page ...
Page 4: ...IV Blank page ...
Page 6: ...VI Blank page ...
Page 10: ...X Blank page ...
Page 14: ...XIV Blank page ...
Page 18: ...Seatex Seapath 200 Installation Manual rev 13 Introduction 4 Blank page ...
Page 22: ...Seatex Seapath 200 Installation Manual rev 13 Specifications 8 Blank page ...
Page 53: ...Seatex Seapath 200 Installation Manual rev 13 Installation drawings 39 ...
Page 54: ...Seatex Seapath 200 Installation Manual rev 13 Installation drawings 40 ...
Page 55: ...Seatex Seapath 200 Installation Manual rev 13 Installation drawings 41 ...
Page 56: ...Seatex Seapath 200 Installation Manual rev 13 Installation drawings 42 ...
Page 64: ...Seatex Seapath 200 Installation Manual rev 13 Appendix A Installation worksheet 50 Blank page ...
Page 80: ...Seatex Seapath 200 Installation Manual rev 13 Appendix C Installation of coax connectors 66 ...
Page 81: ...Seatex Seapath 200 Installation Manual rev 13 Appendix C Installation of coax connectors 67 ...
Page 82: ...Seatex Seapath 200 Installation Manual rev 13 Appendix C Installation of coax connectors 68 ...
Page 83: ...Seatex Seapath 200 Installation Manual rev 13 Appendix C Installation of coax connectors 69 ...