Electrical checks
This section of the manual contains the test procedures for the SBP 29 system’s power
and signal interface cables.
WARNING
These checks must be completed before any power is switched onto the system
Cabling
Visual inspection
Refer to the cable plans and interconnection diagrams, and check all power and
interconnection cables. Any locally fitted plugs and connectors should also be checked
to ensure that the correct types have been used for the specific locations. (Sealed or
spark-proof connectors in areas where flammable gasses may accumulate, etc.)
Ensure that all cable connections have been made according to the cable plan, and that
all connections are tight and secure. Ensure that all cables are correctly laid in conduits,
or are otherwise protected according to the regulations and recommendations laid down
by the vessel’s registering authority. Ensure all protective covers are fastened correctly.
Cable connections and continuity
After the cable connections have been completed and the visual inspection has been
carried out, all the cable cores must be checked for correct connection and continuity.
Refer to the cable plans and interconnection diagrams, and check all interconnection
cables. Any locally fitted plugs and connectors must be checked for shorts or open
circuits. Ensure all cable connections have been made according to the cable plan, and
that all connections are tight and secure.
The check procedure will require two engineers equipped with two-way communication
devices; one will require continuity test equipment, while the other will require a suitable
shorting strap.
Follow the check procedure below for each cable core
1
Position yourselves one at each end of the cable to be checked. Good
communications must be established between you and your assistant.
2
Ensure that the cable to be tested is not connected to any power source.
• If a cable terminates in a plug at the unit, the test will be more easily conducted if
the plug is disconnected.
3
Select one pair of cable cores, and check that the cores are connected to the correct
terminals in the unit.
4
Connect your continuity tester to the two terminals in question and check the
continuity.
SBP 29 Installation Manual
Summary of Contents for SBP 29
Page 1: ...451253 A November 2019 Kongsberg Maritime AS SBP 29 Sub bottom profiler Installation Manual ...
Page 111: ...451253 A 111 Figure 12 862 216859 Drawing files ...
Page 112: ...112 451253 A Figure 13 307904 SBP 29 Installation Manual ...
Page 113: ...451253 A 113 Figure 14 862 218001 Drawing files ...
Page 114: ...114 451253 A Figure 15 871 219193 SBP 29 Installation Manual ...
Page 115: ...451253 A 115 Figure 16 871 219201 Drawing files ...
Page 116: ...116 451253 A Figure 17 388168 SBP 29 Installation Manual ...
Page 117: ...451253 A 117 Figure 18 871 219187 Drawing files ...
Page 118: ...118 451253 A Figure 19 821 219199 SBP 29 Installation Manual ...
Page 119: ...451253 A 119 Figure 20 388235 Drawing files ...
Page 120: ...120 451253 A Figure 21 871 219198 SBP 29 Installation Manual ...
Page 121: ...451253 A 121 Figure 22 388148 Drawing files ...
Page 122: ...122 451253 A Figure 23 315550 SBP 29 Installation Manual ...
Page 123: ...451253 A 123 Figure 24 430751 Drawing files ...
Page 124: ...124 451253 A Figure 25 871 212984 SBP 29 Installation Manual ...
Page 125: ...451253 A 125 Figure 26 407070 Drawing files ...
Page 126: ...126 451253 A Figure 27 448231_1A SBP 29 Installation Manual ...
Page 127: ...451253 A 127 Figure 28 427512 Drawing files ...
Page 128: ...128 451253 A Figure 29 435680 SBP 29 Installation Manual ...
Page 129: ...451253 A 129 Figure 30 444783 Drawing files ...
Page 151: ......
Page 152: ... 2019 Kongsberg Maritime ...