The accumulator is installed to the position shown in the figure.
METHOD FOR CHECKING ACCUMULATOR FUNCTION
k
k
CAUTION
Be sure that no person or obstacle is around the machine before performing the inspection.
Check the nitrogen gas charge pressure as follows.
1.
Place the machine on a firm, level ground.
2.
Hold the work equipment in the maximum reach posture
(arm fully out, bucket fully dumped) at height 1.5 m from
the ground.
3.
Perform the following procedure within 15 seconds.
After the engine stops, the accumulator pressure decreases gradually. You can check only just after the en-
gine stops.
1) Keep the work equipment at the maximum reach pos-
ture, turn the starting switch to OFF position (A), and
stop the engine.
2) Turn the starting switch to ON position (B).
MAINTENANCE
MAINTENANCE PROCEDURE
4-65
Summary of Contents for PC700LC-11
Page 2: ......
Page 23: ...LOCATION OF SAFETY LABELS 5 SAFETY SAFETY LABELS 2 3...
Page 66: ......
Page 316: ......
Page 396: ......
Page 397: ...SPECIFICATIONS 5 1...
Page 401: ...For 7 6m Boom SPECIFICATIONS SPECIFICATIONS 5 5...
Page 402: ...SPECIFICATIONS SPECIFICATIONS 5 6...
Page 426: ......
Page 427: ...REPLACEMENT PARTS 7 1...
Page 434: ......