MAINTENANCE PROCEDURE
MAINTENANCE
4-58
CHECK SWING PINION GREASE LEVEL, ADD GREASE
4
q
Prepare a scale.
1.
Swing 3 times each to the left and right, then stop the
machine.
2.
Remove bolts (1) (2 bolts) on the top of the revolving frame
and remove cover (2).
3.
Insert scale (3) through inspection and maintenance hole
(A) into the grease, and check that height (S) of the grease
is at least 54 mm. If the grease level is low, add grease.
4.
Check if the grease is milky white. If it is milky white, it is
necessary to change the grease. Please contact your
Komatsu distributor.
The total amount of grease is 33 liters (29.7 kg).
5.
Install cover (2) with bolts (1).
Summary of Contents for PC450-8
Page 2: ......
Page 3: ...FOREWORD 11 ...
Page 66: ...SAFETY MAINTENANCE INFORMATION SAFETY 2 42 ...
Page 351: ...SPECIFICATIONS 15 ...
Page 355: ...SPECIFICATIONS SPECIFICATIONS 5 5 6 7m Boom PC450 8 ...
Page 356: ...SPECIFICATIONS SPECIFICATIONS 5 6 6 7m Boom PC450LC 8 ...
Page 357: ...SPECIFICATIONS SPECIFICATIONS 5 7 6 7m Boom PC450LCHD 8 ...
Page 359: ...SPECIFICATIONS SPECIFICATIONS 5 9 7 0m Boom PC450 8 ...
Page 360: ...SPECIFICATIONS SPECIFICATIONS 5 10 7 0m Boom PC450LC 8 ...
Page 410: ...SUPER LONG FRONT BOOM AND ARM ATTACHMENTS ANDD OPTIONS 6 50 ...
Page 436: ...OPERATION HIGH REACH DEMOLITION EQUIPMENT 27M 7 26 3 Extend arm cylinder Arm cylinder ...
Page 469: ...INDEX 18 ...
Page 470: ...INDEX 8 2 ...
Page 473: ...COLOPHON 18 ...