REMARK
When digging is performed by rearward pitch, a sudden stick-
ing in the ground will not occur and smooth digging can be per-
formed.
HARD SOIL CONDITION (HARD CLAY SOIL, SHALE STRATUM, ETC.)
When digging is performed by forward pitch, the machine body
is raised and the end bit sticks much better to the ground when
the blade is tilted.
PUSHING UP OPERATION
1.
Perform digging (A) by straight pitch (1).
If digging (A) should be done gradually, do it by rearward pitch (2).
If the ground is hard, do it by forward pitch (1).
ATTACHMENTS AND OPTIONS
METHOD FOR USING DUAL TILT DOZER EFFECTIVELY
6-15
Summary of Contents for D375A-8
Page 2: ......
Page 11: ...Do not repeatedly handle and lift loads FOREWORD VIBRATION LEVELS 1 9...
Page 13: ...Scale interval of the circles is 1 m FOREWORD INTRODUCTION 1 11...
Page 310: ......
Page 394: ......
Page 395: ...SPECIFICATIONS 5 1...
Page 448: ......
Page 449: ...REPLACEMENT PARTS 7 1...
Page 465: ......