STEP 11

1. INSTALL THE TOP CHIP CHUTE.
2. Use 3 HAND BOLTS and hardware provide and secure tightly
3. PLACE THE NYLON WASHER BETWEEN THE METAL WASHER 

AND THE CHUTE AS SHOWN.

REV 1 

9-19-2019

Summary of Contents for DK2 POWER OPC566E

Page 1: ...gas NV 89103 1 702 331 5353 KINETIC DRUM DOT TOWABLE KOHLER ENGINE 6IN KINETIC DRUM CHIPPER REV 1 9 19 2019 DETAIL K2 INC 1080 Clay Avenue Unit 2 Burlington Ontario Canada L7L0A1 DK2 USA EAST 6245 Ind...

Page 2: ...ed in a crate Remove all sides before you begin NOTE UPON INSPECTION OF PARTS IF YOU FIND ANY DAMAGE OR MISSING PARTS PLEASE CALL DK2 POWER AT 702 331 5353 OR CONTACT US VIA OUR WEBSITE WWW DK2POWER C...

Page 3: ...1 PREPARE TO INSTALL THE AXLE 2 Slide chipper body to hang off side of the crate as shown 3 Have a helper tip the unit forward while you complete the next step Extend the unit off the crate REV 1 9 1...

Page 4: ...STEP 3 1 Tip the unit forward 2 Install the axle using the 2 bolts and hardware provided and tighten REV 1 9 19 2019 2 BOLTS AND NUTS...

Page 5: ...P 4 1 INSTALL THE WHEELS 2 Place the 2 black spacers on the axle first 3 Install the 2 wheel with nuts 4 Wheels should spin free 5 Install end caps Spacers REV 1 9 19 2019 End Cap Washer then Nut and...

Page 6: ...STEP 5 1 INSTALL FEED CHUTE 2 With a helper slide the feed chute hinge pins into place close and latch REV 1 9 19 2019...

Page 7: ...STEP 6 1 Holding the feed chute lay the unit down as shown 2 Prepare to install the front hitch assembly REV 1 9 19 2019...

Page 8: ...STEP 7 1 Install the front hitch assembly 2 Use 8 bolts and hardware provide and secure tightly Use bolts provided both sides REV 1 9 19 2019...

Page 9: ...STEP 8 1 Install the articulated front wheel assembly 2 Use bolt and pin hardware provide and semi tight to allow assembly to raise and lower 3 Raise and pin when towing PIN REV 1 9 19 2019 BOLT...

Page 10: ...STEP 9 1 Install the TOW BAR 2 Use 2 bolts and hardware provide and secure tightly 3 Tip unit forward and lower to level Use 2 bolts provided REV 1 9 19 2019...

Page 11: ...remove the mounting hardware from the frame so as to NOT drop into the cutting chamber 3 You can OPEN the door while removing the hardware to be safe Then reclose the door to mount the chute 4 Mount...

Page 12: ...STEP 11 1 INSTALL THE TOP CHIP CHUTE 2 Use 3 HAND BOLTS and hardware provide and secure tightly 3 PLACE THE NYLON WASHER BETWEEN THE METAL WASHER AND THE CHUTE AS SHOWN REV 1 9 19 2019...

Page 13: ...OVE THE PACKING NUT FROM THE BOLT AND DISCARD IT WILL NOT BE NEEDED AND ONLY IS USED TO RETAIN THE MAIN HARDWARE DURING SHIPPING 3 Install the 2 bolts and bar as shown 4 Remove nut from spring bolt 5...

Page 14: ...attery 2 Use 2 bolts and hardware provide and secure tightly 3 Connect the wiring as shown 4 Be carefull as to not touch your wrench to metal frame when installing the positive red wire Use 2 bolts pr...

Page 15: ...REV 1 9 19 2019...

Page 16: ...13 Engine fixture plate 46 Rear wheel axle 14 Main frame 47 Bearing F207 15 Spacer 35 45 10 48 Roller 16 Kill switch 49 Blade 17 Buckle 50 Frame Switch cover 18 Seal cover right 51 Anvil 19 Belt inner...

Page 17: ...INE OPERATION SAFETY AND MAINTENANCE YOUR UNIT HAS A COMMERCIAL KOHLER ENGINE WITH A 3YR PARTS AND SERVICE WARRANTY FOR WARRANTY IN YOUR AREA CONTACT THE NEAREST KOHLER DEALER VISIT WWW KOHLERENGINES...

Page 18: ...OD ONLY CHILDREN SHOULD NOT RUN THIS EQUIPMENT STAY ALERT OF YOUR SURROUNDING AND PERSONS THAT COULD APEAR IN THE AREA WHILE YOU ARE WORKING LOAD TREES INTO FEED CHUTE THIS IS A GRAVITY DRUM FEED CHIP...

Page 19: ...TO Damage to the product due to misuse mishandling and abuse b Improper installation maintenance and storage c Expendable parts such as nuts and bolts pins and springs wiring and switch components hy...