GTD-110/150
Chapter 4
Installation
93151542-00
4-1
Chapter 4 Installation
4.1 Installation consideration
General
Qualified service technicians should perform the installation of the GTD-110/150 series that comprises
the following operations.
(1) Unpacking each component of the system.
(2) Inspection of the exterior of each component unit and accessory.
(3) Checking the ship’s mains voltage and current capacity.
(4) Determining the installation site
(5) Installing the Display unit
(6) Planning the cable routing and connections
(7) Adjustment and setups
4.2 Unpacking of goods
Unpack your package and check if all of the items stated in the packing list are contained in the
package. If not, report this to an insurance agent for tracing missing goods or a refund.
4.3 Inspection of goods
Carefully check the exterior of each component unit for dents, damage, etc. Also check the inside of
component units for electrical and mechanical damages.
4.4 Siting the units
To achieve best operational performance, the following factors must be considered
.
4.5 Cable routing and connections
(1) The display unit should be grounded to the hull as short as possible. We recommend using a wide
and heavy copper braid or plate to be connected to a grounding stud at the rear of the display unit.
(2) The power supply cable should be connected directly to the ship’s battery to avoid RF noise
conducted from other equipment on board.