Kinetic Solar K-Rack™
Installation guide
Page 31 of 37
27 May 2019
9.5.1.
Top Mount
9.5.1.1.
Open Slot
a)
Insert K-Nut portion of micro inverter mount assembly into top channel of
Rail at 30-degrees.
b)
Install micro inverter and torque to spec.
9.5.1.2.
Closed Slot
a)
Install micro inverter mount assembly into mounting slot of micro inverter.
b)
Insert K-Nut portion of micro inverter mount assembly into top channel of
Rail at 30-degrees and rotate flat.
c)
Tighten and torque to spec.
9.5.2.
Side Mount
a)
Insert K-Nut portion of micro inverter mount assembly into side channel of
Rail at 30-degrees.
b)
Install micro inverter onto mount
c)
Tighten and torque to spec
9.6.
Mount Solar Modules
a)
Position module on the rails (make sure to hold modules securely until properly
fastened). Ensure the first module is square before continuing, as this will affect
the squareness of the array.
b)
Insert the K-Nut of the End-Clamp assembly into the top channel of the rail. Insert
K-Nut of the Mid-Clamp assembly into the top channel of the rail. Slide Mid and
End-Clamps into place against edge of panel